Same-box records
Change Order #46, 7 World Trade Center, Jan 1999 · Box 7DCASNYC-WTC_000172216
Submission of Change Order #46 for $2,168 to provide power supply in room 23-50 at 7 World Trade Center.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.988
Change Order #46 for power circuits, 7 WTC, Dec 1998 · Box 7DCASNYC-WTC_000168561
Ambassador Construction submits Change Order #46 to provide power supply and security equipment circuits at 7 World Trade Center.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.988
Change Order #25 for microwave dish structural support, 7 World · Box 7DCASNYC-WTC_000173879
A memo submits Change Order #25 for $36,199 to install steel supports and beams for microwave dishes on the roof of 7 World Trade Center.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.987
Change Order #025, 7 World Trade Center, Nov 1998 · Box 7DCASNYC-WTC_000168612
Ambassador Construction submits Change Order #025 for structural support work on the roof of 7 World Trade Center.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.986
Change order #108 cover letter, Dec 17 1999 · Box 7DCASNYC-WTC_000171573
Ambassador Construction cover letter dated December 17, 1999 submitting change order #108 for video cable connections at the Mayor's Office of Emergency Management.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.984
Change Order #41 Submission for Antenna Support, Dec 1998 · Box 7DCASNYC-WTC_000171855
Letter detailing Change Order #41 for revised antenna support details installed into beam webs at the Office of Emergency Management.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.984
Revised Change Order #024R submission, Nov 1998 · Box 7DCASNYC-WTC_000171914
Ambassador Construction submits revised Change Order #024R for switch installation at the Mayor's Office of Emergency Management on November 5, 1998.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.981
Change Order #054 for OEM project at 7 WTC, Jan · Box 7DCASNYC-WTC_000171383
Change order #054 from Ambassador Construction dated January 18, 1999 for computer equipment relocation at 7 World Trade Center.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.980
Credit Change Order #27 for LAN room flooring, 7 World · Box 7DCASNYC-WTC_000173872
A memo submits a credit of $481 to replace VCT flooring with painting in the LAN room at 7 World Trade Center.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.980
Credit Change Order #27, LAN room painting, 7 WTC, Nov · Box 7DCASNYC-WTC_000168601
Submission of Credit Change Order #27 for painting the LAN room floor instead of installing VCT flooring at 7 World Trade Center.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.980
Change Order #105 Submission, 7 World Trade Center, Nov 1999 · Box 7DCASNYC-WTC_000168359
Contractor submission for Change Order #105 regarding audiovisual system expansion and library head end drawings.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.980
Change Order #82 submission, 7 WTC, April 1999 · Box 7DCASNYC-WTC_000168431
Contractor submits Change Order #82 for $8,313 to replace the radio room door with a new blast-resistant door.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.979