January 1 3, 1 999
Mr. Glenn Pymento
Department of City Wide Administrative Services
Division of Real Estate Services
1 Centre Street, DRES - Room 2000 North
New York, New York 10007
RE: 7 World Trade Center
Mayor's Office of Emergency
Management-V, 7*, & 23"^ Floors
Change Order #51
Dear Mr. Pymento:
Attached please find change order #51 in the amount of $751.00 submitted by
Ambassador Construction for the following scope of work:
The following changes were made on the marked up adjustable shelving shop drawings,
which were received, from Swanke Hayden Connell.
Storage room 23-24; <$31.00>
Height changed from 99" to 87" high
Closet 23-1 6; <$120.00>
Height changed from 101 3/8" to
90 3/8" high
Room 23-35: $179.00
Added additional unit
Room 23-35 $530.00
Added (40) reinforcement bars and raised
height from 75" to 87"
-Additional delivery charge $15.00
-Installation charge increase $75.00
-Subtotal $648.00
-General Conditions $52.00
-Overhead and Fee $42.00
-Insurance $9.00
Total $751.00