FEB-04-30 :B:02 FROM SILVERSTEJN PROPERTIES ID.2127321207 PAGE 4Z7
ambassador construction co , INC.
OEM
7 World Trade Cent«'
7th & 23rd Roots
February 3, 1998
Page Two
Metal Shelving (Allowance) $5,000.00
Speciaf Doors 10.000.00
Roofing 10,000.00
Fabnc Panels 50.000.00
insulated Panels on Roof 25.000.00
Scaffolding & Miscellaneous Patching 75,000.00
Tetecommunlcatfons (Aliowanoe) 263,000.00
A.V. Work (Allowance) 1,827,106.00
Furniture (Not Included)
Equipment (Not Included} •0-
Gonwal Conditions 75CL55Z.00
Subtotal $10,136,565.00
Overhead i Fee 608,194.00
Ireuranee 1.25% 134.30SLQQ
Total Projwrt Budget $10,679,068.00
Aftematert:
Cooling tower on roof ADD $650,000 00
Alternate *2:
Mecko Shades in fieu of bfinds ADD $33,000.00
QUALIRCAIfCl«S.«uEXCU«KQNS:
> Port Authority fiing and inspection fees
» Overtime, eMtept where bididing requires
• Telephone cabling
► Security cabling and equipment
► Allowenoos for A.V. and teteoommunications work based
on costs in oUftrw specrftcation
•• Equipment and fijmiture not included in costs
► Sales Tax
» Inspection & testing for steel
► Cost foresdsting fuel oil fines
• Elevator Work
* Any work to existing bathroom
Continued,..