NYC 9/11 Public Portal Document
i'
f ■
♦ - .................................................
1^ AMBASSADOR CONSTRUCTION CO.. INC.
// * %
June 11, 1998
Mr. Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
RE: Mayor’s Office of Emergency Management
7 World Trade Center
Hurricane Wall
Dear Mr. Weems:
We are pleased to submit herewith or budget estimate to construct the “Hurricane Wall" in
accordance with Swanke Hayden Connell Architects’ fax message of 5/27/98 for the sum
of FOUR HUNDRED SEVENTY THREE THOUSAND EIGHT HUNDRED SEVENTY
DOLLARS ($473,870.00):
SCOPE OF WORK '
This budget estimate is for changes in the walls over and above the original walls shown on
Addendum 1 drawings dated 5/15/98. We have included the appropriate credits for the
original carpentry and drywall, hollow metal, hardware and special doors which were part
of our original quotation. Our original quotation had included $8,500 for waterproofing
between the curtain wall and the hurricane wall, this value has not been affected by the
change.
The trade value breakdown is as follows:
Demolition (fireproof removal) $5,000.00
Drywall & Carpentry 224,000.00
Hollow Metal <1.756.00>
Finish Hardware <2,800.00>
Electric 20,000.00
HVAC 59,100.00
Iron & Steel 41,600.00
Special Doors <1,822.00>
Blast Proof Doors & Access Doors 60,500.00
Fireproofing 5,000.00
General Conditions 8% 32,706.00
Overhead & Fee 6% 26,492.00
Insurance 1.25% 5JB5(LOQ
Total $473,870.00
Continued.../
317 MADISON AVENUE. NEW YORK, NY 10017. 212 922 1020, FAX 212 949 9762