J. The existing Amtrak tunnels shall be continuously inspected by the
Contractor from the inside. Any damage such as cracks, falling bricks or
loosening of bricks or mortar shall be immediately reported to the Engineer.
The Contractor shall modify his excavation procedure to prevent further
damage. All damage to the tunnels caused by the Contractor's operations
shall be repaired to the satisfaction of Amtrak and the Engineer at no cost
to the Authority.
K. where there is less than four feet of cover above the section line of the
Amtrak tunnels, construction equipment weighing more than 1,000 lbs. gross
weight shall not be used in the backfilling and compaction work. Where more
than four feet of cover exists over the section line, equipment having a
gross weight of up to 10 tons may be utilized.
3.12 EXCAVATION PROCEDURES - TENTH AVENUE BRIDGE AREA
A. Excavation of rock within 50 feet of the Tenth Avenue Bridge may not begin
until broaching in the area of the bridge has been completed to subgrade
elevation. Line drilling in the area may be done in two equal vertical
lifts provided line drilling for each lift is done prior to the start of
production blasting for that lift;
B. The excavation shall proceed in a west to east directiion. Blasting and
excavation of rock east of the centerline of Tenth Avenue may not proceed
until the underpinning of the West Yard Building has been completed.
C. Rock east of the broach line, lying on the easterly property line of Tenth
Avenue, may not be removed prior to excavation of all rock to the west of
this line. Blasting in this area will not be permitted.
D. Removal of rock for a 15 foot width, as measured at right angles to the
broach line at the south abutment, shall be made in sections coinciding with
each section of the abutment stem. A section is defined as that portion
between construction joints. Removal of rock may be made on alternate
sections simultaneously. Sections of rock remaining may not be removed
until adjacent abutment sections have been placed and concrete has achieved
28 day strength. The length of sections as defined above will be increased,
as approved by the Engineer, to allow room for reinforcing bar splices.
3.13’ BACKFILLING
A. General: Backfill with approved backfill material. Place backfill as
promptly as work permits but not until completion of the following:
1. Acceptance by the Engineer of the construction below finish grade
including waterproofing where applicable.
2. Recording of final location and limits of the structure, and of any
utilities or other underground features that will be covered by
backfill.
3. Removal of concrete formwork, trash and debris.
Contract 02220-12 Excavation and
1-02-21064-0-0 Backfilling
NYC-WTC_000165819