Gilse^an, Michael
From: Smyth, Virginia
Sent: Wednesday, February 05, 2003 3:32 PM
To: Schiano, Frank; Fenves, Carol
Cc: Gilsenan, Michael
Subject: Schedule A's for 114 Liberty St.
Attached are Schedule A's for the cleaning and air monitoring contracts being prepared for 114 Liberty. Basically, they are
the same as the ones finalized for 125 Cedar Street. Please let me know if any changes are required. I am also attaching
a draft scope of work for the cleaning contract. As you know, we have extremely tight time contraints, in order to meet
FEMA's requirements for funding. Our timeline is as follows:
2/10/03 - Mailing of bid documents
2/18/03 - Mandatory pre-bid conference (walk-thru)
2/24/03 - Bid Opening
2/26/03 - Commence Work for Air Monitoring Contract
2/28/03 - Commence Work for Cleaning Contract
SCHALBAM.wpd SCHALBCLwpd
1
NYC-WTC_000162822
OCR can misread numbers and units. Confirm readings against the page image before using them.
NYC-WTC_000162822Source: NYC Law Department, mirrored locally
List of contract documents for WTC interior and exterior cleaning work including indemnification boilerplate, bonding requirements, insurance specifications, and general…
Final notice letter from the Department of Environmental Protection dated September 3, 2002, regarding World Trade Center debris observed on 49 Warren Street.