machine-extracted · confidence unavailable · Check page ↗Preliminary scope of work document for cleaning 114 Liberty Street,
Machine-extracted title · confidence 95%Initial draft of the comprehensive scope of work required to safely clean 114 Liberty Street following environmental damage.
NYC-WTC_000155525–000155603Folder label: “114 LIBERTY 2 OF 2”

OCR status: ok · source: pdftotext
NYC 9/11 Public Portal Document
December 17, 2002 114 LIBERTY STREET REMOVAL OF DUST, DEBRIS, AND CONTAMINATED MATERIALS 3.03 FIT TESTING:
A. The Contractor shall ensure that the workers are initially qualitatively or quantitatively fit tested. Fit types of respirators to be actually worn by each individual. An individual shall use only those respirators for which he/she has been trained and fit tested.
B. Whenever the respirator design permits, workers shall perform the positive and negative air pressure fit check each time a respirator is worn in accordance with the requirements set forth in 29 CFR 1910.134, Appendix B-1. Powered air-purifying respirators shall be tested for adequate flow as specified by the manufacturer.
C. Records of respirator fit tests for all personnel shall be provided to the Owner and be available at the work site weekly.
3.04 TYPES OF RESPIRATORY PROTECTION REQUIRED:
A. The Contractor shall provide respirators selected by an Industrial Hygienist that meet the following requirements:
Half-mask and full-face air-purifying respirators with HEPA filters shall be used to reduce the concentrations of airborne asbestos fibers in the respirator below the exposure limits specified by federal, state, and local regulations when the ceiling or the 8-hour time- weighted average airborne concentrations of asbestos fibers are reasonably expected to exceed no more than 10 times those limits.
2. Full-face powered air-purifying respirators (PAPR) equipped with HEPA filters shall be used to reduce the concentrations of airborne asbestos fibers in the respirator below the exposure limits specified by federal, state, and local regulations when the ceiling or the 8- hour time-weighted average airborne concentrations of asbestos fibers are reasonably expected to exceed 10 times, but not more than 100 times, those limits. A supply of charged replacement batteries, HEPA filters and flow test meter shall be available in the clean room for use with powered air-purifying respirators. HEPA filters shall be changed daily or as flow testing indicates change is necessary.
3. Use of single use dust respirators is PROHIBITED for the above respiratory protection
4. NO ONE is to be permitted into the work area without proper respiratory protection.
3.05 MAINTENANCE AND DECONTAMINATION PROCEDURES:
A. Respiratory protection maintenance and decontamination procedures shall meet the following requirements;
Respiratory protection equipment shall be inspected and decontaminated on a daily basis in accordance with OSHA 29 CFR 1910.134, Appendix B-2; and
2. HEPA filters for negative pressure respirators shall be changed on a daily basis; and
3. Respiratory protection shall be the last piece of worker protection equipment to be removed. Workers must wear respirators in the shower when going through decontamination procedures as stated in Section 9, 3.02; and
© AMBIENT GROUP, INC. - 2002 43
RESPIRATORY PROTECTION
NYC-WTC 000155571
OCR can misread numbers and units. Confirm readings against the page image before using them.
Related records
Browse subjects →Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.
Same-box records
47 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.998
machine-extracted · confidence unavailable · Check page ↗Filed elsewhere
NYC-WTC_000155460
Submission of a preliminary scope of work document for safely cleaning the 114 Liberty Street building.
48 shared non-person entities · 1 shared topics · similarity 0.998
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000155168
Draft cleaning procedures and contract documentation for 114 Liberty with minor revisions, shared with EPA for review and comment.
12 shared non-person entities · 1 shared topics · similarity 0.976
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000138892
Forwarding draft cleaning procedures for 114 Liberty Street to EPA for review and comments.
12 shared non-person entities · 1 shared topics · similarity 0.975
machine-extracted · confidence unavailable · Check page ↗12 shared non-person entities · 1 shared topics · similarity 0.974
machine-extracted · confidence unavailable · Check page ↗14 shared non-person entities · 1 shared topics · similarity 0.973
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000107169
Letter from DEP responding to an inquiry by enclosing scopes of work for environmental cleanup at 125 Cedar Street.
17 shared non-person entities · 1 shared topics · similarity 0.973
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000155394
Transmission of cleanup and environmental monitoring documentation for 114 Liberty post-WTC dust remediation project.
14 shared non-person entities · 1 shared topics · similarity 0.973
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000162906
Document tracking the chain of custody for environmental monitoring samples at 114 Liberty Street on February 7, 2003.
14 shared non-person entities · 1 shared topics · similarity 0.973
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000107535
Resident request for DEP to perform cleaning and monitoring work at an apartment in Manhattan.
17 shared non-person entities · 1 shared topics · similarity 0.973
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000155635
Submission of contract changes to scope documents awaiting final approval and bidder lists.
14 shared non-person entities · 1 shared topics · similarity 0.973
machine-extracted · confidence unavailable · Check page ↗More like this page
Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.
Similarity score 1.000 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Similarity score 1.000 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000155460
Submission of a preliminary scope of work document for safely cleaning the 114 Liberty Street building.
Similarity score 1.000 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000125579
Technical specifications document prepared for asbestos abatement work at the 130 Cedar Street site.
Similarity score 0.971 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000150209
Laboratory report listing PCM and TEM asbestos air sampling results collected on September 26, 2001.
Similarity score 0.969 (not a probability)
machine-extracted · confidence unavailable · Check page ↗NYC-WTC_000125579
Technical specifications document prepared for asbestos abatement work at the 130 Cedar Street site.
Similarity score 0.967 (not a probability)
machine-extracted · confidence unavailable · Check page ↗Buildings in this record
Machine-extracted building matches; verify each source. Buildings, never households.
- 114 Liberty Street · 16 pages · confidence 0.70 · verify page 79
Others also read
Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.
Cited alongside this record in an Ask answer
NYC-WTC_000155460
Submission of a preliminary scope of work document for safely cleaning the 114 Liberty Street building.
Cited alongside this record in an Ask answer
Cited alongside this record in an Ask answer
NYC-WTC_000138892
Forwarding draft cleaning procedures for 114 Liberty Street to EPA for review and comments.
Cited alongside this record in an Ask answer
NYC-WTC_000134132
US EPA Region 2 letter dated November 15, 2005, confirming completion of environmental review for abatement plans at 133-135 Greenwich Street.