NYC 9/11 Public Portal Document
Gilsenan, Michael
From: Schiano, Frank
Sent: Wednesday, February 05, 2003 3:46 PM
To: Smyth, Virginia; Fenves, Carol
Cc: Gilsenan, Michael; Hoffer, Mark
Subject: RE: Schedule A's for 114 Liberty St.
Virginia, the Law Department has not approved doing this work on an emergency basis. So, your timeline may have to be
modified.
—Original Message
From: Smyth, Virginia
Sent: Wednesday, February 05, 2003 3:32 PM
To: Schiano, Frank; Fenves, Carol
Cc: Gilsenan, Michael
Subject: Schedule A's for 114 Uberty St
Attached are Schedule A's for the cleaning and air monitoring contracts being prepared for 114 Liberty. Basically, they
are the same as the ones finalized for 125 Cedar Street. Please let me know if any changes are required. I am also
attaching a draft scope of work for the cleaning contract. As you know, we have extremely tight time contraints, in
order to meet FEMA's requirements for funding. Our timeline is as follows:
2/10/03 - Mailing of bid documents
2/18/03 - Mandatory pre-bid conference (walk-thru)
2/24/03 - Bid Opening
2/26/03 - Commence Work for Air Monitoring Contract
2/28/03 - Commence Work for Cleaning Contract
« File: SCHALBAM.wpd » « File: SCHALBCL.wpd »