To: Contract ROF-REMl File
From: Stuart M. Erdfarb, P.g^^
Department of
Environmental Date: April 15,2002
Protection
S9-17 Junction Boulevard
Re: Contract ROF-REMl
Flushing, New York Withdrawal of Bid Due to Error
11373-5108 Safeway Environmental Corp.
On April 10,2002, bids were opened for Contract ROF-REMl, for the
Christopher O. Ward EMERGENCY ROOFTOP AND FACADE REMEDIATION AT THE WORLD TRADE
Commissioner CENTER SITE (the “Contract”). Ten bids were submitted. The low bidder,
with a bid of $547,337.50, was Safeway Environmental Corp.
(“Safeway”). The engineer’s estimate for the Contract was $3,303,000,
and the next lowest bid, submitted by Fiber Control, Inc. was
Stuart M. Erdfarb, P.E. $1,287,337.50. The average of the ten bids is $2,651,918. When the low
AOENCY CHEF CONTRACnNQ OFFICER bid is eliminated, the average increases to $2,885,761. This is a unit price
Td (718)696-3300 contract.
Fax (718) 696-3278
[email protected]
In a letter to the Department, dated April 10,2002, Safeway stated that it
had based its bid on cleaning only theJront of the affected buildings, when
in fact, the Contract calls for the cleaning of each side of the buildings.
According to Safeway, its unit prices for this work omitted a substantial
quantity of work, i.e. the cost of suspending scaffolding for cleaning the
sides and backs of the buildings. In a follow-up letter, dated April 11,
2002, Safeway explained that it used $.96 per square foot instead of $3.09
per square foot of cleaning. Safeway unintentionally omitted a substantial
quantity of work in the compilation of its bid.
Pursuant to §3-02(m)(3)(iii) of the Procurement Policy Board Rules, I, as
Agency Chief Contracting Officer, approve the withdrawal of the bid
submitted by Safeway based on the following:
the mistake was made known the Agency within
three days of the opening of the bids; and.
the price bid was based on an error of such
magnitude that enforcement would be
unconscionable;
the bid was submitted in good faith, and the bidder
submitted credible evidence that the mistake was an
inadvertent omission, as opposed to a judgement
error; and.