the error in the bid is actually due to an unintentional omission of a substantial quantity of
work made directly in the compilation of the bid, which unintentional omission has been
clearly shown by objective evidence drawn from inspection of the original paperwork,
documents or material used in the preparation of the bid sought to be withdrawn; and
it is possible to place DEP in the same position as existed prior to the bid.
The second low bid of $1,287,337, submitted by Fiber Control, Inc., will be processed for award
of the Contract.
cc: Alvatroni
Smyth
Fenves
Wasserman
Schiano
NYC-WTC_000151252