Re: Declaration of Emergency
Written Determination
Contract ROF-REM3
PIN 82602WTCROF3
Stuart M. Erdfarb, P.E.
AOENCT CHEF CONTRACTOM OFFICER
Gentlemen:
Tel (718)696-3300
Fax (718) 696-3278 This letter shall serve as the Written Determination required by §3-06(c)(3) of the
[email protected]
Procurement Policy Board Rules ("PPB Rules”) for the procurement conducted pursuant to
§3-06 of the PPB Rules under a Declaration of Emergency for Rooftop and Facade
Remediation in Sector Three in the Vicinity of the World Trade Center
Site. (Contract “ROF-REM3"). On March 19,2002, oral approval was provided by the
Comptroller and by the Corporation Coimsel. The Declaration of Emergency was signed
by former DEP Commissioner Joel A. Miele Sr., P.E. on March 20, 2002. On April 2,
2002, written approval was provided by the Comptroller and by the Corporation Counsel.
The following narrative is provided pursuant to §3-06(e)(3) of the PPB Rules.
Introduction: As a result of the terrorist attacks on September 11, 2001, buildings in the
area surrounding the World Trade Center site were damaged and destroyed. In the
aftermath of the attacks, in order to minimize further destruction and implications of the
attack, various remediation activities were immediately instituted. As a follow-up to such
activities performed in October and November, 2001, DEP, in conjunction with the United
States Environmental Protection Agency (“EPA”) and the New York State Department of
Labor (“DOL”), performed site visits at buildings in the surrounding vicinity. Although
many buildings were found to be free of debris, the assessments found some buildings
containing debris with various dispersal patters, including isolated debris areas at the
perimeters of roofs, at the base of parapet walls and in gutters. Debris was also visible on
horizontal surfaces on building facades. This debris, characteristic of debris from the
impact of the September 11* attacks, seemed to have reformed into dense caked masses.
Samples collected from buildings visited indicated that asbestos-containing material may
be present.
DEP, in conjunction with EPA, determined that an expedited clean-up of approximately
250 debris-containing buildings is necessary to protect the health and safety of the public.
Such clean-up will require the services of asbestos remediation firms. In order to perform
the clean-up work as expeditiously as possible, it was decided to divide the area to be
cleaned into three sectors, and therefore, three separate contracts were let. The instant
( www.nyc gov/dep J
contract, ROF-REM3 is for those buildings included in Sector 3.
(718) DE P-HELP
NYC-WTC_000150645
OCR can misread numbers and units. Confirm readings against the page image before using them.