Distribution - Various Locations
Manhattan - On January 12, 2001 the discharge from the 40ih Street Pumping Station was revalved.
The northwest regulator at Shaft 18 was also revalved. This work was done to compensate for the
48' inch water main in 7th Avenue, between 401h and 42nd Streets, which was out of service due to
subway station construction.
Capital projects for new water mains were initiated for the following:
- Improved water supply for Lower East Side of Manhattan in the vicinity of Stuyvestant
Town
- New building sites along 149th Avenue at Springfield Lane in Queens.
The Green Building, Battery Park City; Manhattan
DEP staff has completed its review of the site connection proposal application filed by the Albanese
Development Corporation and their consultant on behalf of the Battery Park City Authority for the
`Green Building' project at Terrace and Murray Streets in Battery Park City.
Bypass Discovered near New Stadium
Alerted by a contractor working at the new Yankee minor league stadium in the Saint George area
of Staten Island, agency crews verified that there is a continuing dry-weather bypass of 5 to 10 GPM
occurring at the PR-011 outfall. The outfall is located at Hamilton Avenue, and is discharging raw
sewage into the Upper Bay. By January 9th, our investigations confirmed that at least one building,
185 St. Marks Place, had an illegal connection, and we were following up with monitoring and dye-
testing on three other buildings that were suspected of being improperly connected. The bypass has
been reported to NYSDEC, and to our own Division of Sewer Regulation and Control, which will
direct the reconnection of all improperly connected buildings to the appropriate sanitary sewer.
Mercury Gauge Forum
On January 10, 2001, staff attended a "Mercury Gauge Forum' sponsored by Con Edison/EPA and
held at the Con Edison Learning Center. An overview of mercury hazards was presented including
l+ (twd~ealth risks. The two primary sources of mercury in NYC were discussed which are (1) " ressure
-con arcing regulators
Wa" ~( gauges" which areüea to test the in a en
Co' '" wlkh regulate me gas piessure In bulidhigs. FollowIng die uiscusslons,as
09% ofëVurai non-mercury pressure gauges. In addition to DEP, DOH and DOB had representatives
(~P~✓~n l
• at the meeting.
So
i~ Route 120/22 Project (Kensico Reservoir Basin)
NYSDOT has released the Final Design Report/Final Environmental Impact Statement for the Route
120/22 and I-684 Project in the Kensico Reservoir Watershed. DEP will review the five volume
document to ensure that the issues raised in response to the Draft Environmental Impact Statement
and the Supplemental Draft Environmental Impact Statement have been adequately addressed and
that all potential impacts on the City's Water Supply have been identified and mitigated.