Mr Rajappan Radhakrishnan - NYC DEP
21-23 Thames Street Variance Request
Airtek Project 05-0701- Revised September 29,2005
Project Monitoring: Throughout the decontamination activities, project air monitoring will be
conducted in addition to the Perimeter Monitoring described above. Project Monitoring will be
conducted in strict accordance with RCNY Title 15 Chapter 1, Section 1-41 to 1-45 and
approved variance application. All sample analyses will be by TEM.
Clearance Testing: Aggressive area clearance testing for asbestos will be conducted for all work
areas by TEM.
Clearance Criteria:
Clearance testing for asbestos will be acceptable when all samples for a given work area meet
the 70 structures per square millimeter TEM standard. Additional clearance sampling shall be
performed as specified in the work plan.
Thank you for your time and consideration,
Sincerely,
Michael Porter
Michael Porter
Senior Project Manager
MP:mtf
NYC-WTC 000134159
OCR can misread numbers and units. Confirm readings against the page image before using them.
NYC-WTC_000134159Source: NYC Law Department, mirrored locally
EPA Region 2 letter regarding revised environmental work plan submission for two buildings including asbestos, health, and safety assessment components.
87 shared non-person entities · Same agency, volume and box · similarity 0.990
EPA Region 2 letter regarding revised environmental work plan submission for two buildings including asbestos, health, and safety assessment components.
EPA Region 2 letter regarding revised environmental work plan submission for two buildings including asbestos, health, and safety assessment components.
EPA Region 2 letter regarding revised environmental work plan submission for two buildings including asbestos, health, and safety assessment components.
EPA Region 2 letter regarding revised environmental work plan submission for two buildings including asbestos, health, and safety assessment components.