Part III — Health & Safety Plan
133-135 Greenwich Street/21-23 Thames Street
Airtek Project 05-0701— Rev 3, August 29, 2005
removal and disposal of installed porous and certain nonporous building materials and
components contaminated by settled dust and debris; cleaning and salvage of certain installed
non-porous building equipment and components contaminated by settled dust and debris;
removal of ACBM from the Building; packaging and loading of regulated waste as identified
during the implementation of the Waste Sampling and Management Plan.
Task 4: Deconstruction activities including the cleaning of the building exterior
(i.e. building washdown), floor-by-floor deconstruction and removal of the remaining "clean"
building components including exterior brick flooring and structural wood frame
wall,
components.
Task 5: General site work, including fencing, erecting scaffolding/hoists, paving, if any,
and drainage. Summaries of the potential physical, chemical and biological hazards that may be
encountered during these tasks and the associated hazard control methods are presented in Table
2-1.