Part III — Health & Safety Plan
133-135 Greenwich Street/21-23 Thames Street
Airtek Project 05-0701— Rev 3, August 29, 2005
1.0 INTRODUCTION
This Health and Safety Plan (HASP) presents the practices and procedures that the Contractor
shall implement and enforce during the deconstruction and demolition of the buildings located at
133-135 Greenwich/21-23 Thames Street in New York City (the Buildings). This HASP will be
applicable to all persons entering the Buildings and to all persons working in and around the
Buildings. The deconstruction of the Buildings will occur in two phases:
The Abatement Phase of the Deconstruction Project will occur while the work area is placed
under negative pressure containment and includes the following general categories: (a) the
general area cleanup of WTC dust and debris, (b) removal and disposal of installed porous and
certain non-porous building materials and components, (c) cleaning and salvage of certain
installed non-porous building equipment and components, (d) removal of building materials
containing asbestos which were present in the Building prior to September 11, 2001 (referred to
herein as "ACBM"), primarily within the Building interior, (e) packaging of asbestos and other
regulated waste at generation points, movement of containers to the decontamination unit and
movement of decontaminated containers to waste loading.
The Deconstruction Phase of the Deconstruction Project will occur following the Abatement
Phase and removal all porous and contaminated materials, and will follow conventional
demolition procedures. Deconstruction activities include the following general categories: (a)
floor-by-floor deconstruction and removal of the remaining "clean" building components
including exterior masonry walls, sub-flooring and structural wood frame components, and (b)
general site work, including fencing, erecting scaffolding/hoists, paving, if any, and drainage.
Summaries of the potential physical, chemical and biological hazards that may be encountered
during these tasks and the associated hazard control methods are presented in Table 2-1.
The clean-up and abatement will be conducted so that the Building can be safely deconstructed
in compliance with applicable law to allow for redevelopment of the site.
The Contractor shall be supported on this project by the Owner's Environmental Consultant who
will provide environmental testing, air sampling and asbestos project monitoring and serve the
function of Environmental Consultant/Project Monitor.
1.1 BACKGROUND
The events of September 11, 2001, which caused the destruction of the WTC Towers generated
massive debris and dust. While not physically damaged, some of this WTC dust entered into the
133-135 Greenwich/21-23 Thames Street Buildings. The Buildings had been partially reoccupied
after September 11, 2001 following clearance of debris and unspecified cleaning to permit re-
occupancy.
1.1.1 Environmental Characterization
4
NYC-WTC 000134271