Asbestos Inspection Report
Premise No:
Inspector
Dennis Antzoulatos
SUNDAY
118 FULTON STREET
Inspection Date:
06-23-02
Page 2 of2
5:30PM
WORKERS BEGIN CONSTRUCTION OF A DYKE ON THE STREET TO
COUECT ANE WATER FROM THE SCHEDULED FACADE CLEAN-UPS OF
114-116 FOLTON, 118 FULTON, RO PULTON AND 122 FULTON STROET.
FOR THE PURPOSES OF AIR SAMDUNG THE FACADES OF TUE
FOUR BULLDINGS ULL BE CONSIDERED ONE WORK AREA.
E CONDUCT A VISUAL INSPECTION OF THE FACADES THAT
HAVE JUST BEEN CUEANED AND FIND THAT THEY ARE FOEE
OF ANY WTC DEBRIS.
THE CUEAN-UR PROSECIS AT
118 EULTON AND 120 FULTON STREET ARE NELO COMPLETE.