NYC 9/11 Public Portal Document
130 Cedar Street July 15,2004
Selective Demolition and Façade Restoration Koenen Associates
the submittals. A failure by the Contractor to identify in his letter of transmittal
material deviations from the plans and specifications shall void the submittals
and any action taken thereon by the Architect. When specifically requested by
the Architect, the Contractor shall resubmit such shop drawings, descriptive data
and samples as may be required to evaluate substitutions.
D. If any mechanical, electrical, structural, or other changes are required for the proper
installation and fit of alternative materials, articles, or equipment, or because of deviations
from the contract plans and specifications, such changes shall not be made without the
consent of the Architect and shall be made without additional cost to the Owner.
1.09 TEMPORARY USE OF EQUIPMENT
A. No equipment intended for permanent installation shall be operated for temporary
purposes without the written permission of the Architect.
B. The temporary or trial usage by the Owner of any mechanical device, machinery,
apparatus, equipment or any work or materials supplied under this Contract before final
completion and written acceptance by the Architect, shall not be construed as evidence of
the acceptance of same by the Owner. The Owner shall have the privilege of such
temporary and trial usage, for such reasonable length of time as and when the Architect
shall deem to be proper for making a complete and thorough test of same and no claim
for damage shall be made by the Contractor for the injury to or breaking of parts of such
work which may be caused by weakness of Inaccuracy of structural parts or by defective
material or workmanship. If the Contractor so elects, he may at his own expense, place a
competent person or persons to make such trial usage; such trial usage shall be under
the supervision of the Contractor.
1.10 GENERAL REQUIREMENTS
A. In the event that it is necessary for the Contractor to store any materials offsite, he shall
first obtain the approval of the Architect. The Contractor shall be responsible for
insurance and warehousing charges of any materials stored offsite. The Contractor shall
also be responsible for the cost of delivery to the job site of any material that has been
stored offsite.
B. Materials delivered to the job site shall be carefully stored and protected from damage.
Damaged material shall not be used in the work. The Contractor shall provide, where
directed, temporary storage facilities as may be required for the storage of all materials
which might be damaged by weather.
C. Manufactured articles, materials and equipment shall be applied, Installed, connected,
erected, used, cleaned and conditioned as directed by the representative manufacturers,
unless otherwise specified.
D. Equipment, plant, and appliances, such as hoists, centering, concrete lifts, construction
elevators, cranes, rigging, towers, derricks, walks, ramps, chutes, scaffolding,
implements, transportation, cartage, and other things necessary and required for the
adequate execution of the work and as required by law and applicable Union rules shall
be provided and shall be maintained In good and safe mechanical working order, be
responsible for their safe use, and remove them when no longer required. Applicable
requirements of OSHA shall become and form a part of this document.
E. During handling and installation of work at project site, clean and protect work in progress
and adjoining work on a basis of perpetual maintenance. Apply suitable protective
Materials and Equipment 1600-3
NYC-WTC 000125143
OCR can misread numbers and units. Confirm readings against the page image before using them.