NYC DEP ACP Fax:7185953648 Feb 28 2005 17:07 P.15
IST .COAST tIIAZ•MAT :REMOVAL, INC _
Asbestos Abatement Contractor
494 E 41 Sheet, Paterson, NJ 07504
Phone: (973) 345-0022
Fax (973) 345-4665
Abatement of floor covering/mastic (29,100 SgPt), wall and columns plaster (7,500 sq ft.) and
transits panels (1,080 sq. ft.) ' We shall comply with attachment VA.
We are requesting a variance from the following subsections:
Section 1-81(m): Partial plasticization of the work area(s).
Work Proms
a Posting of Signs
"Danger Asbestos" warning signs, in English, Spanish, and the language spoken by the crew members,
will be posted at all entrances to the working area.
h. Insta~(ation of Worker/Wale Decontarninalion Unit
This will be attached to the work area. This unit will be installed using three chambers divided by air lock
consisting of shower, dirty room, and a clean room. This unit will also be fully sheathed inside using two
(2) layers of six mil fire retardant polyurethane sheeting, and two six mil reinforced polyurethane on the
floor of the decontamination unit. The dean room will include shelves, and clean sealable plastic bags for
storage of clean clothes; the decontamination -unit shall contain shelves for storage of respirators, towels,
respirators filters; and others personal protective equipment The shower room shall contain liquid soap &
shampoo, and disposable towels. Shower water shall be drained, collected and filtered through a water
filtration system. Filtered water shall be discharged to a sewer. The Waste unit will have washroom to
utilize to wash down the single ACM bags, to the double bags.
c. Installation of Critical Barriers.
All. areas will be sealed off with isolation barriers as per ®1-81ac),()). All movable objects will be
removed from the areas. All penetrations in and along the floor will be sealed. The walls of the work area
and any floor surfaces not being abated will be covered with two layers of 6-mil plastic sheeting.
d. Removal of ACM
After establishing six air changes per hour, each abatement team will be equipped with appropriate hand
tools for manual methods of removal ACM. The asbestos containing material shall be removed first, by
wet methods. After the ACM material is adequately wetted will be directly bagged. A visual inspection
will be made by asbestos supervisor to ensure the absence of debris on the floor, after that and one hour
waiting period we will start removal of VAT.
e: Clean-up procedurefBag-Out Sequence.
Upon completion of the stripping, floor tiles shall be rendered free of visible debris. All exposed floor
surface shall be coated with transparent encapsulant Prior to the completion of each shift, the single
disposable bag will be brought over to the de-con unit (wash room), where the bags shall be wetted down
and placed into an additional 6-mil disposable bag. The second disposable will be secured with water
resistant duct tape, labeled and brought down to the waste container for storage until the completion of
work. Upon completion of each work area and acceptable visual clearance, all critical barriers will be
removed and disposed of as ACM and shall follow the same bag out sequence as mentioned above.
We hope this explanation meets with your approval. Should you have any questions or need additional
information, please/eel free to contact me at your earliest convenience in my office.
Removal; Inc.
Project Manager