Regulatory Submittal Part I — Work Plan
Fiterman Hall — 30 West Broadway, New York, New York
Airtek Project 05-0867 —January 10, 2006
3.5 USEPA Notification
Due the fact that the decontamination will constitute a Large Asbestos Project"
according to EPA NESHAP, notification of the project will be made to the
USEPA. A copy of the USEPA notification will be attached to the final version of
the Project Work Plan. In addition, if it is determined that greater than 100 kg of
Hazardous Waste is to be generated in any one month from this site, RCRA
notification of USEPA will be required.
4.0 Utilities - General:
4.1 Electric
The building is presently fed with a temporary service consisting of 800 Amps,
120 / 208 VAC electric power off of a Con Edison meter located in a protective
enclosure and shed situated at the northwest corner of the site. The power
presently feeds a switch providing emergency power for emergency lighting, a
single service elevator, and temporary light stringers. This current electrical
service is insufficient for the needs of the remediation / deconstruction
Contractor; therefore, additional power must be provided.
The mechanical engineering consultant assessed the projected electrical loads, and
prepared drawings showing the scope of the required electrical work. Con Edison
reviewed the load request and the drawings, and determined that its equipment
located in a vault on Barclay Street can adequately meet this requirement. The
Construction Manager will contract with a licensed electrical contractor for the
reactivation of a portion of the original building system.
Con Edison recently inspected the transformer installation located in vaults on
Barclay Street that originally fed the building, and determined that one of the
three transformers in the vault is currently active and the remaining two can be
reactivated. Prior to increasing the power to the building, Con Edison requires
that the existing inactive electrical equipment be cleaned of dust and rust, and
then tested by the licensed electrical contractor. This work is to be conducted
under a re-opening of NYS DOL Variance 05-0919. Con Edison will then inspect
the electrical equipment. Once accepted, Con Edison will direct the electrical
contractor to disconnect the temporary service. Con Edison will then reactivate
the additional transformers.
The licensed electrical contractor will activate power in the main building riser to
the main distribution panel on each floor. All distribution throughout the floor
will be inactive. Power to the passenger and freight elevator will be restored.
The elevator equipment will be gross cleaned and restored to operation by a
licensed elevator maintenance contractor.