NYC 9/11 Public Portal Document
Regulatory Submittal Part I — Work Plan
Fiterman Hall — 30 West Broadway, New York, New York
Airtek Project 05-0867 — January 10, 2006
The remediation/deconstruction Contractor will engage the services of its own
licensed electrical Subcontractor, who will be responsible for tying into the panels
for the purpose of providing lighting, operating HEPA filtration equipment, and
electrically operated tools. The electrical Subcontractor will be responsible for
the system through remediation and deconstruction, including obtaining the final
disconnect notice from Con Edison.
4.2 Plumbing
Presently the personnel decontamination unit (decon) located at the northwest
corner of the property is operated off of water fed from temporary clean water
storage tanks, which are located adjacent to the decon.
The mechanical engineering consultant has prepared plans for providing a source
of potable water for use by the remediation deconstruction contractor. A new
waterline will be extended from a point in the cellar near the existing service
entrance to a point above street level at the proposed location of the decon. The
water will be used for cleaning and operation of the various personnel and waste
decon facilities. Drinking water will be provided by a bottled water vending
service.
The remediation deconstruction contractor will be responsible for extending water
service up through the building for its own needs, and will remove the system and
disconnect the service from the building.
43 HVAC
The HVAC system will not be operated at any time.
4.4 Fire Protection
The existing fire standpipe will be filled, pressure tested, and repaired to make it
ready for use by the FDNY. The standpipe will be operated as a dry system with
hose racks. In the event of an emergency, the FDNY would use a pumper truck
connected to a street hydrant to deliver water through the standpipe.
4.5 Elevator Service
As detailed in Airtek's Re-opening Requestfor Variance 05-0919, 11/14/05 it is
the intent of the Project to utilize the Building elevators to execute the abatement
and demolition removals. Upon completion of the work detailed in the Re-
opening request, operational capability of the building elevator systems will have
been tested, and specific engineering controls and monitoring will be conducted to
allow the elevators to be run safely.
6
NYC-WTC 000095749