Change order #004 systems installation, 7 WTC, Aug 1998 — page 5

WTC 7 / 7DCAS / Mayors Office of Emergency Management 7 World Trade Center - 1, 7 & 23rd Floors Change Order #004 Amb. Job # S57-5175
NYC-WTC_000172032Machine-extracted title
Memo or letter

Summary Change order #004 for $261,029 covering oil tank removal, concrete housekeeping pad, and electrical systems installation.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 — page 1

WTC 7 / 7DCAS / Hurricane Wall®O. E. M.®7 W. T. C.®98-145®Hurricane damper
NYC-WTC_000172054Machine-extracted title
Form

Summary Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. ofContaminants: smoke

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 — page 2

WTC 7 / 7DCAS / Hurricane Wall®O. E. M.®7 W. T. C.®98-145®Hurricane damper
NYC-WTC_000172055Machine-extracted title
Form

Summary Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 — page 3

WTC 7 / 7DCAS / Hurricane Wall®O. E. M.®7 W. T. C.®98-145®Hurricane damper
NYC-WTC_000172056Machine-extracted title
Form

Summary Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 — page 4

WTC 7 / 7DCAS / Hurricane Wall®O. E. M.®7 W. T. C.®98-145®Hurricane damper
NYC-WTC_000172057Machine-extracted title
Form

Summary Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 — page 5

WTC 7 / 7DCAS / Hurricane Wall®O. E. M.®7 W. T. C.®98-145®Hurricane damper
NYC-WTC_000172058Machine-extracted title
Form

Summary Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 — page 6

WTC 7 / 7DCAS / Hurricane Wall®O. E. M.®7 W. T. C.®98-145®Hurricane damper
NYC-WTC_000172059Machine-extracted title
Form

Summary Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 — page 7

WTC 7 / 7DCAS / Hurricane Wall®O. E. M.®7 W. T. C.®98-145®Hurricane damper
NYC-WTC_000172060Machine-extracted title
Form

Summary Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 — page 8

WTC 7 / 7DCAS / Hurricane Wall®O. E. M.®7 W. T. C.®98-145®Hurricane damper
NYC-WTC_000172061Machine-extracted title
Form

Summary Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. ofContaminants: lead

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 — page 9

WTC 7 / 7DCAS / Hurricane Wall®O. E. M.®7 W. T. C.®98-145®Hurricane damper
NYC-WTC_000172062Machine-extracted title
Form

Summary Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 — page 10

WTC 7 / 7DCAS / Hurricane Wall®O. E. M.®7 W. T. C.®98-145®Hurricane damper
NYC-WTC_000172063Machine-extracted title
Form

Summary Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 — page 11

WTC 7 / 7DCAS / Hurricane Wall®O. E. M.®7 W. T. C.®98-145®Hurricane damper
NYC-WTC_000172064Machine-extracted title
Form

Summary Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 — page 12

WTC 7 / 7DCAS / Hurricane Wall®O. E. M.®7 W. T. C.®98-145®Hurricane damper
NYC-WTC_000172065Machine-extracted title
Form

Summary Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 — page 13

WTC 7 / 7DCAS / Hurricane Wall®O. E. M.®7 W. T. C.®98-145®Hurricane damper
NYC-WTC_000172066Machine-extracted title
Form

Summary Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

OMB approval record for project scope, April 8, 1998 — page 1

WTC 7 / 7DCAS / Department of Citywide Administrative Services
NYC-WTC_000172140Machine-extracted title
Unclassified

Summary Record from the Office of Management and Budget authorizing a scope for design services and equipment at 7 WTC.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Unidentified document fragment, 7 World Trade Center, 1998 — page 1

WTC 7 / 7DCAS / OEM 7 World Trade Center
NYC-WTC_000172144Machine-extracted title
Unclassified

Summary Fragmented text containing alphanumeric codes and symbols from a 7 World Trade Center record.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Schedule of computer deliveries, Dec 4 1998 — page 2

WTC 7 / 7DCAS / Schedule of deliveries
NYC-WTC_000172272Machine-extracted title
Memo or letter

Summary Memo dated December 4, 1998, scheduling computer equipment deliveries to 7 World Trade Center requiring electrician assistance.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Fax regarding electrical feed for press, Jan 22 1999 — page 1

WTC 7 / 7DCAS / Mayor's Office of Emergency Management
NYC-WTC_000172274Machine-extracted title
Memo or letter

Summary Correspondence concerning revised consent and memo for running fiber optic and electric cables on the first floor of 7 World Trade Center.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

OEM space construction cost summary, World Trade Center — page 1

WTC 7 / 7DCAS / OEM Space-Where the Money was Spent
NYC-WTC_000172277Machine-extracted title
Unclassified

Summary Financial record detailing contract balances and expenditures for construction and furniture equipment at the Mayor's Office of Emergency Management space.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of

Construction cost estimate for OEM World Trade Center project — page 1

WTC 7 / 7DCAS / BUREAU OF SPACE DESIGN CONSTRUCTION COST ESTIMATE
NYC-WTC_000172283Machine-extracted title
Form

Summary Bureau of Space Design document estimating construction costs for the Mayor's Office of Emergency Management program at the World Trade Center.

No matching passage to preview on this page.

Volume NYC-WTC0007Agency: Citywide Administrative Services, Dept. of