SECTION 02082
implications and risks involved; and understands the use
and limitations of the respiratory equipment to be used.
B. Submit copies of the following items to the Resident Engineer and Construction Manager
during the work:
1. Security and safety logs showing names of person entering work space, date and
time of entry and exit, record of any accident, emergency evacuation, and any
other safety and/or health incident.
2. Progress logs showing the number of workers, supervisors, hours of work and
tasks completed shall be submitted daily to the Resident Engineer and
Construction Manager.
3. Floor plans indicating Contractor's current work progress shall be submitted for
review by the Resident Engineer and Construction Manager at weekly progress
meetings.
4. All Contractor's air monitoring and inspection results.
C. Project Closeout Submittals
1. Upon completion of the project and as a condition of acceptance, the Contractor
shall present two copies of the following items, bound and indexed:
a. Lien Waivers from Contractor, Sub-Contractors and Suppliers,
b. Daily OSHA air monitoring results.
c. All Waste Manifests (Asbestos and Construction Debris), seals and
disposal logs.
d. Field Sign-ln/Sign-Out Logs for every shift.
e. Copies of all Building Department Forms and Permits,
f. A Letter of Compliance stating that all the work on this project was
performed in accordance with the Specifications and all applicable
Federal, State and Local regulations.
g. All WaiTanties as stated in the Specifications,
h. Fully executed disposal certificates and transportation manifest.
1.16 QUALITY ASSURANCE
A. Notification to EPA: Prior to start of the project, the Contractor shall be required to notify the