3.3 Phase II - Structural Deconstruction
Phase 11 - Structural Deconstruction includes the structural deconstruction of the remaining
cleaned steel, large MEP, concrete, and curtain wall as well as cleaning and removal of exterior
and roof, and roof equipment. Phase II will follow successful completion of Phase I work on a
floor. Phase II of this project entails:
• Cleaning of the exterior facade and rooftop of dust and debris;
• Removal and disposal of exterior netting;
• Removal of cooling tower transite ACBM materials, rooftop ACBM caulking, and
exterior faqade aluminum panel ACBM caulking and localized removal of exposed
exterior spray-on fireproofing,
• Structural deconstruction of the Building including removal of all cleaned structural
steel, concrete and large equipment requiring the use of the tower crane for removal^ and
• Backfilling site.