Section 2 - Ambient Air Monitoring Program Revision No.: 0
130 Liberty Street Deconstruction Plan Date: September 7, 2005
Lower Manhattan Development Corporation
1.0 INTRODUCTION
1.1 Project Background and Evolution
This document entitled Ambient Air Monitoring Program for the 130 Liberty^ Street
Deconstruction Project (Plan) represents a revised and combined air monitoring plan
incorporating the following two prior plans: (i) the Draft Plan provided as Section 2 of the Draft
Deconstruction Plan issued by Contractor on December 10, 2004 and (ii) the companion plan
prepared by TRC Environmental Corporation (TRC) entitled Proposed Enhanced Exterior Air
Monitoring Approach and Conceptual Design 130 Liberty Street (October 8 2004). Both of
these documents were issued by the Lower Manhattan Development Corporation (LMDC) in
December 2004 for review and comment by federal, state, and local regulators and the general
public. At the time of release, readers of the two companion plans were advised by LMDC that,
due to their independent development, there were redundancies and a good deal of overlap in the
two plans. For this reason, LMDC intended to revise the two programs to ensure that the
Contractor’s and property owner’s monitoring programs were complementary and contained the
necessary overlap to serve Quality Assurance/Quality Control purposes.
The December 2004 plans were submitted to regulatory agencies for review. Written responses
from the United States Environmental Protection Agency (USEPA), the New York State
Department of Environmental Conservation (NYSDEC), and the New York State Department of
Labor (NYSDOL) addressing the December 2004 plans were provided to LMDC on January 31,
2005. Thereafter, on June 13, 2005 a revised Air Monitoring Plan was submitted to the
applicable regulatory agencies addressing the agencies’ January 31,2005 responses.
Under cover of a letter from USEPA dated July 26, 2005, the regulators provided additional
responses concerning the Air Monitoring Plan. These July 26, 2005 responses have also been
addressed and incorporated into this Plan.
Additionally, subsequent to release of the December 2004 air monitoring plans, an approved
monitoring plan for the deconstruction of 4 Albany Street was issued. This plan, entitled
Specifications for Community Environmental Monitoring During Abatement and Demolition of 4
Albany Street (December 22, 2004), was approved for use by many of the same regulatory
agencies reviewing the deconstruction of 130 Liberty. Accordingly, and at the direction of the
regulators, the Plan adopts many of the features of the 4 Albany Street monitoring program.
Most notably, the Plan adopts the two tiered system of action levels approved for use at 4 Albany
Street.
Once approved, the Plan will be implemented and administered by the LMDC Environmental
Consultant during Phase I and Phase II of the deconstruction of the 130 Liberty Street property.
This Plan does not provide all of the details of the quality assurance/quality control measures that
will be implemented by LMDC. Instead, these measures are addressed in a Quality Assurance
Project Plan (QAPP) that is being submitted contemporaneously herewith and is incorporated
herein by this reference. Compliance with the QAPP is a required component of this Plan.