Asbestos Abatement
sheeting, turning layer a minimum of 12 inches up wall,
and seal layer to wall.
(4) Cover walls with a second layer of 6-mil polyethylene
sheeting, overlapping wall layer a minimum of 12 inches,
and seal layer to floor layer.
(5) In areas where demolition is required to access ACM, a
layer of 6-mil reinforced polyethylene sheeting shall be
placed on the floor of the enclosure.
(6) Perform demolition required to access ACM. Debris
resulting from demolition activities shall be disposed of as
ACM as described in this Specification.
(7) Repeat preparation of areas accessed by demolition
activities as described above.
v) Suspended ceiling tiles and T-grid components shall remain in
place until the preparation of the Work Area below the ceiling tiles
are completed and personnel and equipment decontamination
enclosures have been constructed.
w) Scaffolds shall be provided for workers engaged in work that
cannot safely be performed from the ground or other solid Work
Area surface.
x) Pre-Removal Inspections
a. Prior to removal of
any ACM, the Contractor shall notify the Testing
Laboratory and request a pre-removal inspection. Posting
of warning signs, building of decontamination enclosure
systems, and all other preparatory steps have been taken
prior to notification of the Testing Laboratory.
b. Contractor shall correct any deficiencies observed by
Testing Laboratory at no additional cost to City.
c. Following the Testing Laboratory's approval of the Work
Area preparations, removal of ACM may commence.
2. Removal of ACM Within Full Containment:
a) Mist material with amended water. Allow sufficient time for the
amended water to penetrate the material to be removed.
CAPITAL PROJECT NUMBER PO79201K 02081-75
100: CONTRACT DOCUMENTS REV. May 3,2000
- 75 -100% CONTRACT DOCUMENTS
REV. 0: DATE
CITY_21MC100_006631324
NYC-WTC_000416836
OCR can misread numbers and units. Confirm readings against the page image before using them.