NYC 9/11 Public Portal Document
Asbestos Abatement
interpreted to extend Engineer's responsibility into Contractor's
responsibility for construction supervision.
3. Eurnish: Except as otherwise defined in greater detail, term "furnish" is used
to mean supply and deliver to project site, ready for unloading, unpacking,
assembly, installation, etc., as applicable in each instance.
4. Indicated: The term "indicated" is a cross-reference to graphic
representations, notes or schedules on Drawings, to other paragraphs or
schedules in the Specifications, and to similar means of recording
requirements in Contract Documents. Where terms such as "shown,"
"noted," "scheduled," and "specified" are used in lieu of "indicated," it is for
purpose of helping reader locate cross-reference, and no limitation of
location is intended except as specifically noted.
5. Install: Except as otherwise defined in greater detail, term "install" is used to
describe operations at Project site including unloading, unpacking, assembly,
erection, placing, anchoring, applying, working to dimension, finishing,
curing, protecting, cleaning and similar operations, as applicable in each
instance.
6. Installer: The tenn "installer" is defined as the entity (person or firm)
engaged by Contractor, or its subcontractor or sub-subcontractor for
performance of a particular unit of work at Project site, including
installation, erection, application and similar required operations. It is a
general requirement that such entities (installers) be expert in operations they
are engaged to perform.
7. City: The term "City" is defined as City of New York Department of Design
and Construction. City of New York Department of Design and Construction
has been authorized to coordinate construction activities at the site relating to
the project described in the Contract Documents
8. Provide: Except as otherwise defined in greater detail, term "provide" means
furnish and install, complete and ready for intended use, as applicable in
each instance.
9. Testing Eaboratory: The term "Testing Eaboratory" is defined as an entity
engaged by City and Resident Engineer to perform specific inspections or
tests of the work, either at Project site or elsewhere; and to report and (if
required) interpret results of those inspections or tests.
B. Definitions Relative to Asbestos Abatement:
1. Abatement: Procedures physically taken to control fiber release from
ACM. This includes removal, encapsulation, enclosure, and repair.
CAPITAL PROJECT NUMBER PO79201K 02081-11
100: CONTRACT DOCUMENTS REV. May 3,2000
- 11 -100% CONTRACT DOCUMENTS
REV. 0: DATE
CITY_21MC100_0 06631260
NYC-WTC_000416772
OCR can misread numbers and units. Confirm readings against the page image before using them.