NYC Law Department release
Independent mirror · updated as the City releases more · v1.5.1
☕ Buy me a coffee
← Document results/Unboxed/No folder label
Document / 2 pages

FEMA project worksheet, PS 234, 2001

Machine-extracted title · confidence 28%

FEMA project worksheet for PS 234 air monitoring and testing schedule.

NYC-WTC_000385785–000385786
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Parameter Temperature (T) Summer: 73-79 degrees at 50% RH ASHRAE 55 Winter: 68-75 degrees at 50% RH Relative Humidity (RH) 30-60% ASHRAE 55 Carbon Dioxide (CO2) <700 parts per million (ppm) above ASHRAE 62 background level Carbon Monoxide 9 ppm USEPA NPAAQS (as sited in ASHRAE 62)_____________________________ Total Volatile Organic Compounds 1 ppm AIHA (TVOC) Respirable Particulates (PM 25) 65 micrograms per cubic meter of air USEPA NPAAQS-G for general population USEPA

USEPA= United States Environmental Protection Agency NPAAQS= National Primary Ambient-Air Quality Standard AIHA= American Industrial Hygiene Association ASHRAE= American Society of Heating, Refrigerating, and Air Conditioning Engineers

Contract Costs

The total contract cost from February 5, 2002 to June 30, 2002 is estimated to be $343,518.92. A letter of explanation from the vendor and specific information pertaining to the ambient air sampling completed at PS 234 is attached to this PW. The following information from the applicant and the applicant’s vendor was used to compute the total eligible cost:

The first set of contract costs cover the period from February 5, 2002 to February 11, 2002, a seven-day period. The cost per day for this first section of the contract is $849.67 per day (see attached letter from the vendor). Additionally, the second set of contract costs cover the period from Febmary 12, 2002 to June 30, 2002, a 139-day period. The cost per day for the second section of the contract is $2,428.57 per day. The vendor stated that the reason for the increase in cost per day from the first section of the contract to the second section of the contract is that the BoE had requested additional testing stations, tests, and analyticals. The following table demonstrates how the costs in this PW were derived.

Contract Dates Cost Per Day Number of Total Days

02/05/02 to 06/30/02 $2,428.57 139 $337,571.23 TOTAL ELIGIBLE 146 5343,518.92

Percentage of Work Completed

The percentage of work complete was calculated through April 22, 2002. As such, for 77 days of the 146-day period, the work performed by ATC Associates has been completed. The BoE has not been invoiced for these costs, and therefore the dollar amount in this PW is based on an estimate provided by the applicant’s vendor, ATC Associates.

77 days/ 146 day period = 77/146 = 53% of the work complete.

CITY_21MC100_009214602

NYC-WTC_000385786

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000385786Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000411648

FEMA worksheet detailing air-testing locations and schedule for PS 833.

Similar indexed content

Compare copies and versions →