Chain-of-custody, WTC dust cleanup project, 6/02

Machine-extracted title · confidence 33%

Draft chain-of-custody outlining regulatory compliance for dust cleanup and air sampling after WTC attack.

NYC-WTC_000363042–000363048
Page image
Page image not rendered yet.
The pipeline renders page images incrementally; check back or read the OCR text alongside.
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Indoor Air Residenitial Assistance Program Monitoring Contract Scope of Work DRAFT - 6/11/02

A. Introduction All work performed under this contract must be in compliance with all applicable, relevant, and appropriate regulations and this Scope of Work, including but not limited to those of the United States Environmental Protection Agency (USEPA), the United States Department of Labor, Occupational Safety and Health Administration (USOSHA), the New York State Department of Labor (NYSDOL), the New York State Department of Health Environmental Laboratory Approval Program (ELAP) and the New York City Department of Environmental Protection (NYCDEP). This project shall involve scheduling, coordinating and monitoring the clean up of dust/debris and air sampling from building apartments impacted by the attack and collapse of the World Trade Center.

B. Roles and Responsibilities The USEPA On-Scene Coordinator (OSC) has overall responsibility for insuring that work conducted as part of the Indoor Air Residential Assistance Program is completed safely, efficiently and in a compliance with the Scope of Work. As such, the OSC or designee shall have the following authorities relating to work conducted under this contract:

1. The OSC has the authority to stop workfor health and safety reasons or for non- compliance with the Scope of Work.

2. The OSC has the authority to direct the contractor in the performance of the work.

3. The OSC has the authority to review and approve or disapprove of the qualifications of all contractor personnel involved in the work.

4. The OSC has the right to inspect and accept or reject any work.

[input DEP Roles and Responsibilities for contract officer and project manager]

C. Qualifications Proof of qualifications must be presented upon request, including qualifications for wipe sampling, personal monitoring, HVAC and mold expertise.

Project Monitors The Project Monitors must possess valid NYS Asbestos Project Monitor certificates. Project Monitors must have served as a third party project monitor on at least 20 asbestos abatement projects. Project Monitor must have performed final clearance inspections on at least 50 asbestos abatement projects. The Project Monitor must have access to translation services to conduct

1

CITY_2IMCl00_000439056 NYC-WTC_000363042

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000363042Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

Compare copies and versions →