1. Need timeline for Herman Miller completion.
2. Need timeline for Novalink completion.^-"
3. Week of December 1, build Compaq racks in remote Data'
4. December 07, Data Rooms Available (Clean and Powered).
5. December 07, Begin Installation of Cabletron hubs. Wire hubs and servers.
6. December 14, Need wiring of power and data to furniture (Herman Miller and
Novalink) complete.
7. Week of Decemberl4, begin Workstation install.
NYC-WTC_000173733