Project timeline notes for IT infrastructure at 7 WTC, Nov

Machine-extracted title · confidence 95%

List of scheduled tasks including rack building, power availability, and workstation installation dates for the data center dated November 10, 1998.

NYC-WTC_000173733

Folder label: “None

Page image
Scanned page image, NYC-WTC_000173733
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Contractor Meeting 11/10/98 11:00 am

1. Need timeline for Herman Miller completion. 2. Need timeline for Novalink completion.^-" 3. Week of December 1, build Compaq racks in remote Data' 4. December 07, Data Rooms Available (Clean and Powered). 5. December 07, Begin Installation of Cabletron hubs. Wire hubs and servers. 6. December 14, Need wiring of power and data to furniture (Herman Miller and Novalink) complete. 7. Week of Decemberl4, begin Workstation install.

NYC-WTC_000173733

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000173733Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Filed elsewhere

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000167290 · Box 7DCAS

Internal memorandum from DCAS regarding space design for the Mayor's Office of Emergency Management at 7 World Trade Center.

Filed in the same folder

Compare copies and versions →