OEM Budget accounting
Breakdown of the Project's Budget: November 24, 1998
Construction cost Budget $14,287,986.00
Construction cost Budget (Revised) $13,727,986.00
Less Landlord's contribution $1,668,858.00
Maximum amount chargeable to City $12,059,128.00
Construction cost approved on 6/2/98 $12,864,619.00
Amount approved on 7/8/98 $117,684.00
Amount approved by CO on 8/11/98 $7,000.00
Amount approved by CO on 9/14/98 $102,705.00'
Amount approved by CO on 9/21/98 $28,442.00
Amount approved by CO on 10/22/98 $26,483.00
Amount approved by CO on 10/30/98 $42,887.00
Total approved Change order cost $277,782.00
Total construction cost approved $13,260,085.00
Less Landlord's contribution $1,668,858.00
Amount chargeable to City $11,591,227.00
Balance remaining in budget $^;67,901.00