Bulletin #1: Port Authority comments on MOEM work, undated

Machine-extracted title · confidence 95%

A document listing Port Authority comments and associated cost adjustments for the Mayor's Office of Emergency Management renovation.

NYC-WTC_000173277–000173278

Folder label: “Bulletin # 1 (Port Authority Comments)®Sheet 1

Page image
Scanned page image, NYC-WTC_000173278
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

Sheetl

MAYOR'S OFFICE OF EMERGENCY MANAGEMENT 7 WORLD TRADE CENTER I NEW YORK

BULLETIN #1 (HURRICANE WALL-A)

Description of work Ambassador's Cost Revised proposal

1 Additional labour and framing for new duct openings X $5,600.00 314,000.00

2 Patch Twenty two (22) existing columns $2,800.00

3 Add 24 LF of Hurricane wall thru columns $1X400.00 $9,000.00

4 Add one layer of sheetrock on 200LF of Hurricane wall 10^ 314,300.00

5 Deletion of top of wall approximately 300LF firm ($18,000.00

6 F&l 201 pieces of 8"x8"x1/2" steel plate reinforcement at 19 blast proof access doors and 7 blast proof doors $13,750.00

7 Remove existing column fronts at 19 locations $; LOO $1,750.00

8 Leak detection system adiitional cost $1 ,9F5.00 $0.00

9 Electrical work on Hurricane damper 22 locations $20,700.00 J__ 10 Additional steel 3’'x3"x 5/16" welded to spandrel $1 ,165.00 $14,800.00

11 Additional work on Hurricane dampers duct to duct refabricating and install new duct at 4 locations $ 144.00 $8,212.00

12 Additional work on Hurricane dampers and fire/smoke dampers 15 locations; refabricating and installing new duct $3 wtsoo $30,794.00

13 Hurricane damper with flexible connections at 5 locations $: 1.00 $7,305.00

14 Hurricane damper with grill at 32 locations 12; 741,00 $26,356.00

15 Hurricane damper above wall at 32 locations 00 $58,487.00

16 Ruskin dampers Model #CD80;\AF4 with 45" water gauge static pressure 88each $61,560.00

17 10"x10" architectural grills 32 each Sa $4,560.00

118 Vavcon Hurricane damper actuator in duct work $35,150.00 I I 19 Credit original amount in budget for hurricane wall dampers ($^ ($40, SfiS .00)

____ Sub-total $285,^1.00 $245,524.00 General conditions 8% $22,866.48 $19,641.92 Sub-total $308,667.48 $265,165.92 ____ Fee 6%____________________________________________ $18,521.85' $15,909.96 ____ Sub-total___________________________________________ $327,2-fe.33 $281,075.88 Insurance 1.25% $4,09p.24 $3,513.45

TOTAL $331,309.57 $284,589.32

I

Page 1

NYC-WTC_000173278

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000173278Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 · Box 7DCAS

NYC-WTC_000172034

Cost comparison table for Hurricane Wall work items under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.959

machine-extracted · confidence unavailable · Check page ↗
Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 · Box 7DCAS

NYC-WTC_000172020

Cost comparison table for Hurricane Wall work items under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.

3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.956

machine-extracted · confidence unavailable · Check page ↗
Revised Change Order #004, 7 WTC, Sep 1998 · Box 7DCAS

NYC-WTC_000172050

Revised Change Order #004 submitted by Ambassador Construction Co. Inc. for $294,338 regarding work at the Mayor's Office of Emergency Management dated September 11, 1998.

1 shared non-person entities · Same agency, volume and box · similarity 0.951

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000168669 · Box 7DCAS

Memo submitting revised Change Order #004 for oil tank and electrical panel work at the Mayor's Office of Emergency Management.

Similar indexed content

Compare copies and versions →