Same-box records
Revised Change Order #4 Memo, 7 World Trade Center, Sept · Box 7DCASNYC-WTC_000168669
Memo submitting revised Change Order #004 for oil tank and electrical panel work at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.905
Letter re: OEM estimate response, June 1998 · Box 7DCASNYC-WTC_000173319
Letter from Ambassador Construction responding to the Division of Citywide Administrative Services regarding project estimates.
1 shared topics · Same agency, volume and box · similarity 0.902
Fuel oil tank room proposal for 120 Wall Street, May · Box 7DCASNYC-WTC_000172854
Proposal from Benjamin Maintenance Corp. dated May 1, 1998 to prime and coat fuel oil tank rooms at 120 Wall Street.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.898
Bulletin #1 cost sheet, 7 WTC OEM, Sep 1998 · Box 7DCASNYC-WTC_000172054
Detailed cost itemization for Hurricane Wall work under Bulletin #1 at the Mayor's Office of Emergency Management dated September 14, 1998.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.897
Change order #004 systems installation, 7 WTC, Aug 1998 · Box 7DCASNYC-WTC_000172028
Change order #004 for $261,029 covering oil tank removal, concrete housekeeping pad, and electrical systems installation.
1 shared topics · Same agency, volume and box · similarity 0.897
Revised Change Order #004 for OEM, September 1998 · Box 7DCASNYC-WTC_000173810
Letter from Ambassador Construction submitting revised Change Order #004 for oil tank cradle and housekeeping pad work at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.897
Revised Change Order #004, 7 World Trade Center, Sept 1998 · Box 7DCASNYC-WTC_000173445
Ambassador Construction submits revised change order for electrical and concrete work at 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.897
Revised Change Order #4 memo, 7 World Trade Center, Sept · Box 7DCASNYC-WTC_000168684
Memo submitting revised Change Order #4 for oil tank and annunciator panel work at the Mayor's Office of Emergency Management in 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.896
Revised change order #4 submission, Sept 1 1998 · Box 7DCASNYC-WTC_000172098
Letter submitting revised change order #4 for concrete work and panel installation.
1 shared topics · Same agency, volume and box · similarity 0.895
Revised Change Order #004, 7 WTC, Sep 1998 · Box 7DCASNYC-WTC_000172050
Revised Change Order #004 submitted by Ambassador Construction Co. Inc. for $294,338 regarding work at the Mayor's Office of Emergency Management dated September 11, 1998.
1 shared topics · Same agency, volume and box · similarity 0.894
Bulletin #1: Port Authority comments on MOEM work, undated · Box 7DCASNYC-WTC_000173279
A document listing Port Authority comments and associated cost adjustments for the Mayor's Office of Emergency Management renovation.
1 shared topics · Same agency, volume and box · similarity 0.893
Letter regarding Change Order #004, August 1998 · Box 7DCASNYC-WTC_000173453
Letter from Ambassador Construction submitting Change Order #004 for concrete and electrical work at 7 World Trade Center.