Subcontractor estimate form with handwritten notes, 1998

Machine-extracted title · confidence 88%

Ambassador Construction Company estimate form containing handwritten calculations and notes regarding construction work.

NYC-WTC_000172786

Folder label: “OEM, 7 World Trade Center

Page image
Scanned page image, NYC-WTC_000172786
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

05/Ol-.''9S 07:04

Con fin on fnJ MnrbJe /n c ••'r.rr - •rrr.r'r'—.-.-rr.r^5ss«T".-.«sssvsassr.;2s?r!ri->‘:'--.7 -aw. .. • •.fri*.’—■ s-,;;

Alarb; JI tv • Ceramic Tile • Commercial • Residential

FACSIMILE

Date: May 1, 1998

To; Mr. Jack Klein Company: AMBASSADOR CONST

Facsimile No.,

From; Tom McNamara Re. OEM, 7 World Trade Center

No of pages including cover sheet 1

Jack-

Price breakdown is as follows

Slate pavers at lobby 28,000,00 Ceramic tile 23,800,00 Work per 11/012 9,000.00

BID TOTAL 60,800,00

Let me know if you have any other questions on this. Thanks.

Tom McNamara

39^4 ZJtii ‘Y -1 H , New York‘i fioi / Tcl. iVs-TBO-yjO? / Fax: 718-780-9427

NYC-WTC_000172786

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000172786Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

RFI log cover sheet, Sep 1998 · Box 7DCAS

NYC-WTC_000166743

Cover sheet for the Request for Information log documenting 37 received RFI items for the 7 World Trade Center project as of September 16, 1998.

1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.870

machine-extracted · confidence unavailable · Check page ↗
Construction cost estimate, 7 WTC OEM, Feb 1998 · Box 7DCAS

NYC-WTC_000170825

Ambassador Construction submits a $10.8 million cost estimate for demolition and fit-out work at the Mayor's Office of Emergency Management.

1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.870

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Page similarity is temporarily unavailable or this page has no indexed vector.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000168699 · Box 7DCAS

Ambassador Construction submits Change Order #001 for sheetrock wall offset installation at 7 World Trade Center.

Similar indexed content

NYC-WTC_000168702 · Box 7DCAS

Ambassador Construction submits Change Order #001 for sheetrock wall offset work at 7 World Trade Center.

Similar indexed content

NYC-WTC_000171766 · Box 7DCAS

Cover letter submitting Change Order #44 for $24,307 to install fuel oil piping at 7 World Trade Center.