AMBASSADOR CONSTRUCTION CO, INC.
Mayor’s Office of Emergency Management
7 World Trade Center
1, 7 & 23rd Floors
Amb. Job #857-5175
jAs of October 9,1998
CJl# Date Scope_.of Work Price Status
001 7/28 Sheetrock wall offset $7,000.00 Approved
002 7/31 Baltimore Air Coil circuit cooling $9,818.00 Void
003R 8/26 F&l plug mold outet... $3,704.00 Approved
004R 9/11 Delete concrete and reinforcing $294,338.00 Approved
005 9/4 City of NY attached letter $117,684.00 Approved
006 9/8 Additional cost for furnish door 01A $406.00 Approved
007R 9/23 Audio Visual Work and Equipment <$289.803.00> Approved
008 9/10 Change door 01B from a full lite $11,688.00 Approved
009 9/14 As per marked-up wood door $11,707.00 Approved
010 9/15 F&l (1) special class package $2,666.00 Approved
oil 10/1 Change door 05 from hollow metal $2,898.00 Approved
012 10/5 As per FSK-E5 to provide volmeter $7,766.00 Pending
013 10/5 As per FSK-E5-25 additional framing $985.00 Pending
014 10/7 As per attached letter from Cosentini <$5,216.00> Pending
015 10/8 As per SHC sketch for new sleeve $21,234.00 Pending
016 10/15 On Drwg El-23 dated 9/25/98 $37,862.00 Pending
017 10/16 P&l add’l floor boxes under raised $5,042.00 Pending
018 10/19 The Sharp XG-E3000 U $16,761.00 Pending
c:\wpdocs\oem[oemcos.wpdj
317 MADISON AVENUE, NEW YORK, NY 10017, 212 922 1020, FAX 212 949 9762
NYC-WTC_000166719