Cost breakdown between EOC not EOC OEMbrk2
________________ OEM________________
__________ 7World Trade ^nter__________
Cost Breakdown, with all change orders, as of
3/9/99. Total ratio/remarks Not EOC EOC
EOC/project
Demolition $13,000 42.47% ___ $7,479 $5,521
Drywall carpentry $390,000 42.47% $224,367 $165,633
Hollow metal $13,120 42.47% $7,548 $5,572
Finish hardware $30,109 42.47% $17,322 $12,787
Ceiling $289,400 42.47% $166,492 $122,908
' Electric $3,784,400 62.67% $1,412,717 $2,371,683
HVAC $1,433,676 61.65% $549,815 $883,861
Plumbing $389,675 42.47% $224,180 $165,495
^Oj^
Painting $53,100 42.47% $22,552
Floor base_________________________ $150,935 42.47% $86,833 $64,102
Iron Steel $187,325 42.47% $107,768 $79,557
“ $0
Masonary_________________________ $29,000' 0.00% $29,000
Cement & Concrete $103,325 42.47% $59,443 $43,882
Sprinkler $152,400 42.47% __ $87,676 $64,724
Architectural_______________________ $178,250 42.47'% $102,547 $75,703
G]^s& Glazing____________________ $22,700 42.47% $13,059 $9,641
Ceramic Tiles______________________ $29,600 42.47% $17,029 $12,571
Woodwork $‘256,930 42.47% $147,812 $109,118
Purchase Items____________________ $15,509 42.47% $8,922 $6,587
Raised Floor_______________________ ' $92,300 100.00% $0 $92,300
Manhole Covers____________________ $1,515 _______ o.oo‘% $1,515 _____ $0
Marble stone_______________________ $5,711 0.00% $5,71 < _____ $0
Venetian Blind_____________________ $19,200 0.00%' __ $19,200 ______$0
Metal Gtes_______________________ $121,000 0.00% $121,000 _____ $0
Fire Proofing_______________________ $7,000 42.47% $4,027 $2,973
Roofing___________________________ $49,700 o.o‘o% $49,700 $0
Furniture__________________________ $291,143 100.00% $o' $291,143
Audio Visual_______________________ ‘$1,823,937 85.00% $273,591 $1,550,346
Fabric Wall Panel " $19,800 42.47% $11,391 $8,409
Folding wall $14,000 o.‘o‘o%' $14,000 $0
Metal panel $18,000 0.00% $18,000 $0
Special doors______________________ $34,630 4Z47% $19,923' $14,707
Metal shelving $11,726 0.00% $11,726 ______ $0
Safe doors $4,130 0.00% $4,130 $0
Rolling fire door____________________ $2,892 0.00% $2,892 ______ $0
Cut & patch ‘ $30,000 42.47% "'$17,259 $12,741
Generator test $4,500 100.00%' _______ $0 $4,500
W/ire mesh part $3,250 0.00%' $3,250 ______ $0
Subtotal '________________ $10,076,888 $3,877,870 $6,199,018
Overhead +generai Condition+ insurance $1,603,333' $617,008 $986,325
Total bid price $11,680,221 $1V680721 $4,494,878 $7,185,343
Generators $717,890 $717,890
fiJE Fees; Revised $91,500 42.47% $52,640 $38,860
Hurricane Wall $473,870 $473,870
Existing Fuel Lines $302,410 $302,410
Electrical Tappings $219,800 42.47% $126,451 $93,349
Subtotal $13,485,691 $4,673,969 $8,811,722
Scope Reductions $503,388 See "X" beiow $503,388
Subtotal $12,982,303 $4,673,969 $8,308,334
Cost of change orders up to CO#71 $741,704 71.51% $211,347 $530,357
Total $13,724,007 $4,885,316 $8,838,691
Landlord's Contribution $1,668,858
City’s Cost $12,055,149
Cost breakdown by trade Cost todate %
General Construction $5,644,686 41.13% $2,009,331 $3,635,355
Mechanical________ $2,132,198 15.54% $758,996 $1,373,203
Electrical $5,305,019 38.66% $1,888,420 $3,416,599
i Plumbing/ sprinklers $642,104 4.68% $228,569 $413,535
Subtotal $13,724,007 $4,885,316 $8,838,691
! Landlord Contribution $1,668,858
City's Cost to date $12,055,149
X $977,258-473,870
Page 1