Cost breakdown for 7 World Trade Center construction, Mar 5, · Box 7DCASNYC-WTC_000173966
Financial summary dated March 5, 1999, detailing the cost allocation by trade and total city share for the 7 World Trade Center project.
1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.946
DCA letter negotiating change orders #35-71 at 7 WTC, Nov · Box 7DCASNYC-WTC_000171352
Letter from DCA to a property firm confirming negotiated costs for Change Orders #35 through #71 at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.930
Fax cover sheet, DCAS Real Estate Services, Mar 1999 · Box 7DCASNYC-WTC_000171781
Fax cover sheet from DCAS Real Estate Services transmitting documents regarding space design for the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.929
Approval of multiple change orders, 7 WTC, Feb-Mar 1999 · Box 7DCASNYC-WTC_000168471
City correspondence reviewing and negotiating costs for numerous submitted change orders related to facility work.
1 shared topics · Same agency, volume and box · similarity 0.929
Change order review correspondence, 7 World Trade Center, Aug 1999 · Box 7DCASNYC-WTC_000168379
Letter from Citywide Administrative Services reviewing and negotiating costs for multiple change orders at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.926
Approval of Change Orders 93, 97, 99 & 100 for · Box 7DCASNYC-WTC_000171334
Letter from DCAS approving costs for four change orders related to electrical and audiovisual work at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.925
Cost estimate correspondence, 7 WTC, June 1998 · Box 7DCASNYC-WTC_000173153
DCAS letter to contractor regarding cost estimates for Mayor's Office of Emergency Management work at 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.924
Change order approvals #93, #97, #99 & #100, 7 WTC, · Box 7DCASNYC-WTC_000168365
Department memo approving costs for shade motor installation and circuit work at the Mayor's Office of Emergency Management facility.
1 shared topics · Same agency, volume and box · similarity 0.923
Funding request for OEM traffic feed installation, April 1999 · Box 7DCASNYC-WTC_000172953
Memo dated April 27, 1999 requesting funding from the construction budget for metro traffic feed and dish installation at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.922
DCAS letter on negotiated change orders #73-95, Nov 1999 · Box 7DCASNYC-WTC_000171646
Letter from DCAS confirming review and cost negotiation for ten change orders submitted by a contractor for the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.921
DCAS letter re: cost estimates, Mayor's OEM project, June 1998 · Box 7DCASNYC-WTC_000173151
Letter from DCAS referencing original and revised cost estimates for the Mayor's Office of Emergency Management renovation.
1 shared topics · Same agency, volume and box · similarity 0.921
Change Order #65 approval letter, X-ray equipment, Jan 1999 · Box 7DCASNYC-WTC_000167168
Letter approving Change Order #65 for the supply and installation of X-ray and video badging equipment at 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.920