Electrical work estimate, Mayor's Office 7 WTC, June 1998 · Box 7DCASNYC-WTC_000172475
Revised electrical work estimate from Forest Electric Corp. for the Mayor's Office of Emergency Management at 7 World Trade Center.
4 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.984
Electrical work proposal, Forest Electric Co., May 1998 · Box 7DCASNYC-WTC_000172684
Revised electrical work proposal from Forest Electric Co. for the Mayor's Office of Emergency Management at 7 World Trade Center covering multiple floors.
3 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.978
Electrical proposal, ADCO Electrical Corp., May 1998 · Box 7DCASNYC-WTC_000172686
Revised electrical work proposal from ADCO Electrical Corporation for the Mayor's Office of Emergency Management on the 26th floor at 7 World Trade Center in May 1998.
1 shared non-person entities · Same agency, volume and box · similarity 0.906
Letter regarding Change Order #004, August 1998 · Box 7DCASNYC-WTC_000173453
Letter from Ambassador Construction submitting Change Order #004 for concrete and electrical work at 7 World Trade Center.
1 shared topics · Same agency, volume and box · similarity 0.903
Change order #004 systems installation, 7 WTC, Aug 1998 · Box 7DCASNYC-WTC_000172028
Change order #004 for $261,029 covering oil tank removal, concrete housekeeping pad, and electrical systems installation.
1 shared topics · Same agency, volume and box · similarity 0.902
Construction proposal, 7 WTC floors 1, 7, 23, June 1998 · Box 7DCASNYC-WTC_000173352
Revised construction proposal for Mayor's Office of Emergency Management work at 7 World Trade Center totaling $11,645,746.
1 shared topics · Same agency, volume and box · similarity 0.902
Electrical service proposal, 7 World Trade Center, May 1998 · Box 7DCASNYC-WTC_000172671
Contractor proposal for electrical panels, risers, generators, fire alarm, wiring, and lighting work at 7 World Trade Center totaling approximately $3.76 million.
2 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.899
Ambassador Construction revised proposal, June 1998 · Box 7DCASNYC-WTC_000173073
Revised construction proposal from Ambassador Construction for work at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.898
Response to Bulletin #1 regarding generator installation, August 1998 · Box 7DCASNYC-WTC_000173254
A letter detailing the installation of graphic annunciator panels and wiring for generators at the Mayor's Office of Emergency Management.
3 shared non-person entities · Same agency, volume and box · similarity 0.896
Revised proposal submission, 7 World Trade Center, June 10, 1998 · Box 7DCASNYC-WTC_000172123
Contractor submits a revised proposal totaling $11.6 million for demolition and construction work at 7 WTC.
1 shared topics · Same agency, volume and box · similarity 0.896
Initial construction proposal for Mayor's Office, May 1998 · Box 7DCASNYC-WTC_000173355
Ambassador Construction Co. submits an initial $11.4 million proposal for renovation work at the Mayor's Office of Emergency Management.
1 shared topics · Same agency, volume and box · similarity 0.895
Revised construction proposal for Mayor's OEM floors, June 1998 · Box 7DCASNYC-WTC_000173147
A revised construction proposal from Ambassador Construction Co. Inc. for demolition and renovation work on the 1st, 7th, and 23rd floors of 7 World Trade Center.