NYC 9/11 Public Portal Document
'MAY 06 1999 16:29 PR AMBASSADOR CON. TO 6693640 P.02/03
ambassador construction co., INC.
May 6, 1999
Mr. Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York. NY 10048
RE: Mayor's Office of Emergency Management
7 World Trade Center -1. 7 & 23rd Floors
Change Order #085
Amb.Jcb_iLSi57-S125
Dear Mr. Weems;
We are pleased fo submit herewith our change order #085 to perform the following work at
the above referenced premises for the sum of THIRTY FOUR THOUSAND FOUR
HUNDRED ONE DOLLARS ($34,401.00);
SdOPEOEJWQRK
Wnile laying out the route of the fuel-oil lines, the building's elevator inspector from Otis
was in the elevator pits. We showed him the route the fuel-oil lines were taking, and he
informed us the route would not work. When they test the elevators, the counter weights
would interfere with the piping. Therefore a new route has to be taken and the following
additional work has to be performed in order to install the piping;
Masonry
- Remove and reinstall block work around two (2)
doors. Open two (2) holes in masonry between
elevator cars 21 and 1. Replace block upon
completion. $5,200.00
Carpentry
- Reset two (2) existing doors end frames $900.00
Continued...
317 ADISON AVENUE • NEW YORK. NY 10017 • 212922 1020 ■ FAX 2l 2 943 9762