ftPR 16 1999 10=59 PR PMBRSSRDOR CON. TO 6693640 P.02/02
AMBASSADOR CONSTRUCTION CO.. INC.
April 16, 1S99
Mr. Walter Weems
Silverstein Properties, Inc. I
7 World Trade Center
New York, NY 10048
RE: Mayor's Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floors
Amb. Job #857-6175
a£DC.O.#60______
Dear Mr. Weems:
W* are pleased to submit herewith our revised change order #80 to perform the following
work at the above referenced premises for the sum of ONE THOUSAND SIX HUNDRED
THIRTY ONE DOLLARS ($1,631.00).
SCQEEDE.WORK
*- Removal of additional floor granite that was required
because of the interference with steel and splice plate
with fuel oil piping - more investigative work was
required
stonework $1,407,00
General Conditions (8%) 113.00
Overhead and Fee (6%) 91.00
Insurance ...JTfLQQ
TOTAL...... $1,631.00
Please sign (1) copy of this letter and return it by fax to our office.
We trust the above meets with your approval and we look for ward to the continued
pleasure of serving you.
/
Ver^ruly yours, . /
C^STftUCTIpN CO., INC.
Martin schneid^
Vice President
MS;db
cc: Juan Mejia - SHC
Glenn Pymento - DCAS
ACCEPTED: DATED: