NYC Law Department release
Independent mirror · updated as the City releases more · v1.3.3
☕ Buy me a coffee
← Document results/7DCAS/Reorganization of overhead cabling 7 World Trade Center, 7th Floor
Document / 1 page

Memo re: overhead cabling reorganization at 7 World Trade Center,

Machine-extracted title · confidence 95%

A January 14, 2000 memo regarding the reorganization of overhead cabling and reimbursement disputes for work at 7 World Trade Center.

NYC-WTC_000172171

Folder label: “Reorganization of overhead cabling 7 World Trade Center, 7th Floor”

Page image
Scanned page image, NYC-WTC_000172171
OCR text

OCR status: ok · source: pdftotext

NYC 9/11 Public Portal Document

a Mayor’s Office of Emergency Management 7 World Trade Center, 23™ Floor New York, N.Y. 1 [ililg48

Mr. Walter Weems January 14, 2000 Building Manager Silverstein Properties 7 World Trade Center New York, N.Y. 10048

RE: Reorganization of overhead cabling 7 World Trade Center, 7'*^ Floor

Dear Mr. Weems:

In reference to the brief phone discussion of January 12, 2000, and the following letter dated January 7, 2000 concerning the work that was initiated by American Express Bank. Your letter states work was needed for the installation of OEM’s generators and water tank, as well as the removal and relocation of the piping containing numerous communications cables for American Express had to be performed. I have received this letter and the attached invoices that are being submitted by American Express for reimbursements.

At this time I am not in the position to approve the payment of these invoices. The amount for these invoices should not appear as additional rent on OEM’s February rent statement. I will meet with Glenn Pymento, DCAS and John Hughes, OEM Project Manager to discuss this issue.

I will contact you as soon as possible on the outcome of this meeting. If you have any questions please do not hesitate to call.

Sincerely,

Raymond M. Lynch OEM Facilities Manager

CC: Jerome M. Hauer Jack Trabitz John Hughes Glenn Pymento

NYC-WTC_000172171

OCR can misread numbers and units. Confirm readings against the page image before using them.

NYC-WTC_000172171Source: NYC Law Department, mirrored locally

Related records

Browse subjects →

Ranked by indexed similarity. Reasons describe shared subjects and filing context; check the source records.

Same-box records

Change Order #91 Memo, MOEM 7th Floor, August 1999 · Box 7DCAS

NYC-WTC_000172576

Memo submitting Change Order #91 for $6,565 to remedy water leakage on the 7th floor of 7 World Trade Center associated with the Mayor's Office of Emergency Management.

1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.919

machine-extracted · confidence unavailable · Check page ↗
Change order #85 submission, 7 WTC, May 1999 · Box 7DCAS

NYC-WTC_000168420

Letter submitting change order #85 for $34,401 to install new piping for re-routed fuel oil lines, including masonry work.

1 shared non-person entities · 1 shared topics · Same agency, volume and box · similarity 0.911

machine-extracted · confidence unavailable · Check page ↗

Filed elsewhere

No available related records indexed in this group.

More like this page

Similar subjects in other documents. Similarity does not establish the same event, measurement or conclusion.

Others also read

Readers open these alongside this record — through an Ask answer, the same folder, or indexed similarity. Not a claim they are about the same event.

NYC-WTC_000136542

Archival folder label from the Office of the Mayor for World Trade Center records, identified as Folder 0139.

Cited alongside this record in an Ask answer

Compare copies and versions →