NYC 9/11 Public Portal Document
The City of New York
Sii Office of the Mayor
OFFICE OF EMERGENCY MANAGEMENT
100 Church Street - 20th Floor
New York, NY 10007
To: Martin Schneider V.P. Ambassador Construction
From: John E. Hughe OEM Project Manager
Subject: RG-6U Plenum Cable
Date: December 22,1998
As per our conversation, please have Local 3 Electricians pull RG -6U Plenum
Cable from telephone closet “A” to the following locations:
• Room 23-23 (LAN - into A/V termination point)
• Room 23-42 (PIU)
/
• Room 23-38 (Conference/Library)
• Room 23-05 (Mayor’s Suite)
/
• Room 23-51 (W/C Supvervisor) /s /
• Room 23-21 (Pantry)
/ f
• Rooms 23- 37, 34,26, 19,09,17,14 and two lines to Room 23-27.
This represents a total of fifteen (15) pulls. If you have any questions please
contact me forthwith. Thank you.
cc: G. Pymento, DC AS
J. Mejia, Swanke
J. Klein, Ambassador
NYC-WTC_000171861