AMBASSADOR CONSTRUCTION CO, INC.
0
December 2, 1998
Mr. Walter Weems
Silverstein Properties, Inc.
7 World Trade Center
New York, NY 10048
RE: Mayor’s Office of Emergency Management
7 World Trade Center -1, 7 & 23rd Floors
Change Order #026R
Amb. Job # S57-5175
Dear Mr. Weems:
We are pleased to submit herewith our revised change order #026R to perform the
following work at the above referenced premises for the sum of TWELVE THOUSAND
FIVE HUNDRED NINETY NINE DOLLARS ($12,599.00):
SCOPE OF WORK
As per Swanke Hayden Connell’s revised sketches FSK-12 and 40 dated 11/2/98 and
FSK-43 dated 11/24/98. The following is the cost breakdown:
Djywall
- Close Door opening
- Scar patch after demolition J?
- Patch electrical outlets in room #23-07 ?■ $850.00
Ceilings
- Patch ceiling after demolition $850.00
Electrical
- Recircuit lights, relocate switch, delete switch. 600.00
- Relocate devices in room #23-07 300.00 ’
- Add outlets in room #23-11, separate circuit for refrigerator $1,369.00 ’
Appliances
- Add sub-zero refrigerator $1,125.00 c
Forward...