JAN 29 ,’99 15:42 FR AMBASSADOR CONSTR. C0212 949 9762 TO 6693640 P.04/05
AMBASSADOR CONSTRUCTION CO., INC.
♦
Mr. Walter Weems
Silverstein Properties, inc.
January 29, 1999
7 World Trade Center
New York, NY 10048
Re: Mayor's Office of Emergency Management
7 World Trade Center
1,7 and 23rd Floor
Change Order #063
Amb..Jok#S57-517.5
Dear Mr. Weems;
We are pleased to submit herewith our change order #063 to perform the following
options at the above referenced premises for the sum of ONE THOUSAND NINE
hundred twelve dollars ($1,912.00):
1. As per R.B. Samuels Work Order #28501;
- Furnish and install one (1) pipe sleeve through hurricane
wall for FD-MTD mobile terret dispatch. Run cable (FBO)
also for EMS-CAD as requested by OEM (John Hughes).
Labor 2 hours $192.00 (
2. As per R.B. Samuels Work Order #28505:
- Run cat 5 cable from 23-18 to 23-50 add booster in middle
of run re-crimp 3-RJ45 jacks and add 110Volt 15Amp
receptacle for booster located in AA/ enclosure in OEC
area. As requested by OEM (John Hughes).
Labor 4 hours $383.00
Material ... _30.00^
$413.00
3. As per R.B. Samuels Extra Work Order #28507:
- Furnish and install plugmold in room 23-18 as requested
by OEM. •9 '
Labor 3 hours $288.00
Material 54.00 7
$342.00
Continued. ..