AMBASSADOR CONSTRUCTION CO., INC.
January 18, 1999
Mr. Walter Weems
Silverstein Properties Inc.
7 World Trade Center
New York. NY 10048
RE: Mayor's Office of Emergency Management
7 World Trade Center
1. 7 & 23rd Floors
Change Order #054
Amb. Job #557-5178
Dear Mr Weems:
We are pleased to submit herewith our change order #054 for work performed on a
time and material base requested by the OEM and DCAS for the sum of TWO
THOUSAND SIX HUNDRED SEVENTY DOLLARS ($2,670.00):
SCOPE OFWORK
As per R.B Samuels work order #26341 the electricians took delivery of various
computer equipment and moved it to the P I U. room on the 23rd Floor.
This work was performed on regular and overtime hours as per the following:
Straight time 19 hours x 95.80 $1,820.00
Overtime 3.5 hours x 138.35 484.00
Subtotal $2,304.00
General Conditions 184.00
Overhead & Fee 149.00
Insurance 33.00
Total $2,670.00
We trust the above meets with your approval and we look forward to the continued
pleasure of serving you.
Continued...