NYC 9/11 Public Portal Document
Silverstein Properties, Inc
/ Worirj I rade (.li-nloi
New York N Y KJIiAS
I nlf ‘ h'VChStiH
February 1, 1999
Mr. Glenn Pymento
Department of City Wide Administrative Services
Division of Real Estate Services
1 Centre Street, DRES - Room 2000 North
New York, New York 10007
RE: 7 World Trade Center
Mayor's Office of Emergency
Management-V', 7*, & 23"* Floors
Change Order #66_____________
Dear Mr. Pymento:
Attached please find change order #66 in the amount of $15,460.00 submitted by
Ambassador Construction for the following scope of work:
As per Swanke Hayden Connell's sketch SK-56B for the work in the Press Room:
Audio Visual:
Furnish and install floor boxes with plates. Relocate wiring and cable under floor.
$3,943.00
Electrical:
Relocate fire alarm devices. Ground raised floor. Power outlet conversions to new raised
floor.
Labor (38 Hours) $3,640.00
Material $405.00
$4,045.00
Computer Raised Floor:
Remove existing floor and steps. Reinstall existing floor. Supply and install (1) step with
(2) risers. Supply and install fascia. Cut and trim (2) cable cutouts.
$4,750.00
Painting $300.00
Flooring $300.00
Subtotal $13,338.00
General Conditions $1,067.00
NYC-WTC_000168491