November 15, 1999
Ms. Catherine T. Giliberti
Silverstein Properties, Inc
7 World Trade Center
New York, New York 10048
Re: Change Order # 98 & 103
Mayor’s Office of Emergency Management
7 World Trade Center
New York, New York
Dear Ms Giliberti:
We write with reference to CO # 98 & 103 submitted by Ambassador Construction Company on
9/30 & 11/3/99 respectively.
The change orders have been reviewed and the costs have been approved as shown below:
CO# Description of Work Amount Approved
98 Various electrical fighting changes in Press Room
and Mayor’s conference room. $ 8,800.00
103 Press feed. Press Room camera and three (3) wireless
microphones $ 73,987.00
Total $ 82,787.00
In view of the foregoing an amount $82,787.00 is hereby approved, subject to audit, for the above change
orders.
The following is a breakdown of the project’s budget.
Construction Cost Budget $14,287,986.00
Construction Cost Budget (revised) $14,287,986.00
Less Landlord’s Construction $ 1,668,858.00
Maximum amount Chargeable to City $12,619,128.00
Construction cost approved on 6/2/98 $12,864,619.00
Amount approved by CO on 7/8/98 $ 117,684.00
NYC-WTC_000168363