Construction cost approved on 6/2/98 $12,864,619.00
Amount approved by CO on 7/8/98 $ 117,684.00
Amount approved by CO on 8/11/98 $ 7,000.00
Amount approved by CO on 9/21/98 $ 102,705.00
Amount approved by CO on 10/22/99 $ 28,442.00
Amount approved by CO on 10/30/98 $ 42,887.00
Amount approved by CO on 12/01/98 $ 125,453.00
Amount approved by CO on 1/4/99 $ 3,941.00
Amount approved by CO on 1/25/99 $ 78,288.00
Amount approved by CO on 2/10/99 $ 22,721.00
Amount approved by CO on 3/11/99 $ 220,262.00
Amount approved by CO on 3/25/99 $ 4,874.00
Amount approved by CO on 4/8/99 $ 85,000.00
Amount approved for fuel oil line $ 130,000.00
Credit amount approved for previously approved fuel line ($ 85,000.00)
Credit amount approved by CO on 9/9/99 ($ 419.00)
Amount approved by CO on 10/27/99 $ 32,110.00
Amount approved by CO on 11/15/99 $ 82,787.00
Amount approved by CO on 11/16/99 $ 50,000.00
Amount approved by CO on 11/22/99 $ 136,001.00
Amount approved by this CO $ 8,072.00
Total construction cost approved $14,111,731.00
Less Landlord contribution $ 1,668,858.00
Amount chargeable to the City $12,442,873.00
Balance remaining Budget $ 176,255.00
If you have any question, please call Glenn Pymento at (212) 669-8094 or myself at (212) 669-8086.
Thank you for your cooperation.
Sincerely,
/
y
Richard J Ramos
Executive Director of Space Design/DRES
M.Mathew, DRES^RO^
cc: G. Pymento, DRES/
V. Castagnola, DRES J. Menasce, DRES
J. Domingvez DRES W.Weems,Silverstein Properties, Inc
C:/mydoc/constbud/oenVgiliberti6/mm