NYC 9/11 Public Portal Document
DEPARTMENT OF CITYWIDE ADMINISTRATIVE SERVICES
DIVISION OF REAL ESTATE SERVICES
MUNICIPAL BUILDING, - Room 2002 S
NEW YORK, N.Y. 10007
(212) 669-8086 FA.X (212) 669-3640
WILLIAM J. DIAMOND LORI FIERSTEIN
Commissioner Deputy' Commissioner
February 17, 2000
Ms. Catherine T. Giliberti
Silverstein Properties, Inc
7 World Trade Center
New York, New York 10048
Re: Invoice
Mayor’s Office of Emergency Management
7 World Trade Center
New York, NY
Dear Ms Giliberti:
We write with reference to the invoice submitted by 7 World Trade Co. L.P. dated February 4, 2000.
As of this date, this office has approved a total amount of $ 14,133,187.00 for the construction work of the
project and the maximum amount payable by the City is $12,464,329.00. Out of this amount, payment of
$11,684,322.00 has already been made and the balance payable is only $780,007.00.
As per agreement dated August 30, 1999, an amount of $400,000.00 to be retained for Port Authority sign
offs. Therefore, maximum amount that can be paid against your above referred invoice is $380,007.00
only.
In view of the above, we request you to revise and resubmit the invoice for a total amount of $380,007.00.
Following is the accounting of the project’s payment:
Construction cost budget $14,287,986.00
Less landlord’s contribution $ 1,668,858.00
Maximum amount chargeable to City of New York $12,619,128.00
NYC-WTC_000168335