NYC 9/11 Public Portal Document
Mayors Office of Emergency Management Project
8/30 I
September I
9/6 I 9/13 I 9/20 | 9/27 |
October
10/4 | 10/11 | 10/18 | 10^ 11/1 I
WoMBmtoer I
11/8 I 11/15 I 11/22 I 11/29 I
Dacwwbw
12/6 | 12/13 | 12/20 | 12/27 |
[
1/3 | 1/10 | 1/17
JP. Task Name____________ Duration Start
1 Purchase Order Approved Id 9/1/98 Hem
2 Order Material Id 9/4/98 ^Engineering
3 Material Delivery 60d 9/7/98 ^Motorola
4 Develop site Drawings 30d 9/7/98 |ram Manager
5 CCSI Staging 29d 11/2/98
6 CCSI Staging Build 25d 11/2/98 lotorola
7 CCSI Customer Demo 2d 12/7/98 iM,Motorola
8 Ship to #7 WTC/Sites AS 2d 12/9/98 Motorola
9 #7 WTC 23 Floor- WC 65d 10/2/98 5 I
10 Site Preparaton 50d 10/2/98 Samuels,Motorola,Swanki
11 Install CEB Room lOd 12/11/98 Samuels, 'SO,Motorola
12 Install 4 Console Furnitur 8d 11/27/98 Samuels,Motorola,FSO
13 Install 3 Console Electro tOd 12/11/98 FSO,Mot< rola
14 Install Premisys in LAN 5d 12/11/98 l,Motorola
15 Install RCH3000 units lOd 12/18/98 F SO,Motorola
16 #7 WTC Root Radio Room/A 49d 10/19/98
17 Site Prep at #7 WTC Ror 30d 10/19/98 Swanl(e,Samu( Is
18 Install Electrical on roof lOd 10/19/98 Samuels,Motorola
19 Install Antenna Mounts a lOd 10/19/98 imuels,Motorola
20 Install Ant and lines at #7 5d 11/2/98 Samuels,Motorola
21 Install radios on Roof lOd 12/11/98 FSO,Mot< rola
22 Install riser cables 5d 10/19/98 Samuels,Motorola
23 System Optimization lOd 1/1/99 |FSO,Mot
24 Training 3d 1/15/99 Mo
25 Acceptance Testing 5d 1/15/99
26 Final Sign Off Id 1/22/99
Task Milestone Rolled Up Task
Project: NYC Mayor's OEM Project
Date: 8/3/98 Progress Summary Rolled Up Milestone
Prepared by Robert Hudson Page 1
NYC-WTC_000167941